How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsNo
AI workloads
StatusLikely
234MW modern greenfield (2023+)
Phases
Phase 1 · Operational40 MW, target 2024
Full build (JHR01-04) · Under construction234 MW
Who is behind it
OperatorK2 Strategic (Kuok Group) · Colocation
Funder, EquityKuok Group
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Who builds it
Core and shell builderSunway Construction · RM192.88m (≈US$43m) · Oct 2023 Confirmed source ↗ Build contract, letter of initial appointment
Core and shell builderSunway Construction · RM132.7m (≈US$30m) · Feb 2025 Confirmed source ↗ Stages 1 and 2
Core and shell builderSunway Construction · RM260m (≈US$59m) · May 2025 Confirmed source ↗ Stage 3, final phase
Land
Industrial estateSedenak Tech Park (JCorp / TPM Technopark) · 60 acres Reported source ↗ K2 building on a 60-acre parcel in Sedenak Tech Park; seller/terms not stated
Power supply
Grid supplyTNB · 300 MW · 275kV · Apr 2024 Confirmed source ↗ Electricity Supply Agreement; 300MW is gross grid capacity; 275kV interim supply · Applies to the whole campus.
Water and cooling
CoolingHybrid air and liquid cooling · design PUE <1.38x Confirmed source ↗ JHR04 building: air and liquid hybrid cooling (JHR01-03 are direct air)
CoolingAir cooled · design PUE 1.4 Confirmed source ↗ Direct air cooled