Rayong (Eastern Economic Corridor), Rayong, Thailand · EEC (Eastern Seaboard) market · location approximate to city level

K2 Data Centres BKK31-32, Rayong is a data center project in Rayong (Eastern Economic Corridor), Thailand, operated by K2 Data Centres (K2 Strategic). It is at the land and permitting stage. It is planned for 50 MW of IT load.

Open on the mapSuggest a correction
Stage
Land and permitting
Planned IT load
50 MW
Running now
Not disclosed
Operators rarely publish this
Operator
K2 Data Centres (K2 Strategic)
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsNo

AI workloads

StatusLikely

Operator states air-and-liquid hybrid cooling and explicitly targets hyperscalers, cloud providers and AI (K2 site, updated Oct 2025). Liquid-cooling capability is designed-in, but no dated deployment or named AI tenant, so not 'confirmed'.

Phases

BKK31-32 (16 data halls) · Land and permitting50 MW, target 2026

Stage history

2025-10-04Land and permitting · k2strategic.com

Who is behind it

OperatorK2 Data Centres (K2 Strategic) · Colocation
Funder, EquityKuok Group

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Land
Site32.8 acres Confirmed source ↗
Site area only; seller/estate not disclosed
Water and cooling
CoolingHybrid air and liquid cooling · design PUE <1.4x Confirmed source ↗
Air and liquid hybrid cooling (campus page)

Sources checked 2026-09-13

  1. k2strategic.co
  2. k2strategic.co
  3. forbes.com

More in EEC (Eastern Seaboard)

Also run by K2 (Kuok)

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-26.