How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusLikely
Operator states it is Thailand's first facility purpose-built for large-scale GPU clusters / AI training; 250MW greenfield announced 2025; Microsoft reported as anchor for its Thailand cloud region.
Phases
Phase 1 · Under constructionSize not published, target 2027
Who is behind it
OperatorTrue Internet Data Center (True IDC) · Colocation
Funder, EquityCharoen Pokphand Group
Funder, EquityGlobal Infrastructure Partners
Client, reported, unconfirmedMicrosoft
Client, reported, unconfirmedSIAM.AI Cloud
Money at this site
Announced investment, 2026-04THB 77bn (about US$2.4bn)
The figure covers the whole campus.
Platform deals that include it
Microsoft Thailand country investment programme
Country programme, 2026-03US$1.0bn
Global Infrastructure Partners investment in True IDC
Platform acquisition, 2025-05Not disclosed
Platform capital spans several sites. It is never added to this project's own figure.
Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from?
Tell us.