ArusGrid tracks 4 active data center projects operated by DCI Indonesia, with 919 MW of planned IT load, across Indonesia. Of these, 1 is operational, 2 are operational and expanding and 1 is at the land and permitting stage. Disclosed running capacity is 121 MW.
ArusGrid classes the operator as colocation. The largest project is DCI H2 Campus (H2-01, H2-02), Karawang at 600 MW in Greater Jakarta, operational and expanding. AI workloads are confirmed at 1 site. Named funders across its projects are Salim Group, Anthoni Salim and Gallant Venture. No tenant is disclosed at any of its projects, which is normal for colocation and says nothing about occupancy.
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| DCI H2 Campus (H2-01, H2-02), Karawang | Karawang | Expanding | 600 | 27 | DCI Indonesia | Likely |
| DCI H1 Campus (JK1 to JK6), Cibitung | Cibitung, Bekasi | Expanding | 300 | 75 | DCI Indonesia | Confirmed |
| DCI E1, Downtown Jakarta | Jakarta | Operational | 19 | 19 | DCI Indonesia | Unlikely |
| DCI Bintan Campus (Hyperscale 3 / H3) | Bintan | Land and permitting | none published | undisclosed | DCI Indonesia | Likely |
All operators · Full directory