Google India AI Hub (Visakhapatnam) is a data center project in Visakhapatnam, India, operated by AdaniConneX. It is under construction. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Latest change on record: moved to under construction on 28 April 2026.
Next gate to watch: Builder appointed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How India approves, powers and taxes data centers is on Data center rules in India.
Construction or financing is evidenced, or several independent signals agree. On record: named funder, disclosed client (confirmed), committed or approved capital, three or more sources, dated source in the last 24 months. Criteria.
Hyperscaler AI hub announced 2025 at gigawatt scale; no dated GPU or cooling disclosure yet.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.
Full campus, gigawatt-scale, US$15bn 2026 to 2030 · as of 2025-10-14
Adani's own release names Google as the user of the AdaniConneX-built Visakhapatnam campus; Google's India blog (28 Apr 2026) says it will operate an AI data centre there with AdaniConneX and Nxtra. Adani Enterprises Q1 FY27 results report a 400MW hyperscale order in Vizag without naming the customer.
Source · Adani and Google Partner to Build India's Largest Data Centre Campus in Visakhapatnam (Adani Group, 2025-10-14)
Source · Google AI Hub - Scaling India's AI Infrastructure and Community Impact (Google India blog, 2026-04-28)
The figure covers several facilities.
ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.
All projects in Visakhapatnam · All projects in India · All AdaniConneX projects · All projects under construction · Data center rules in India · Full directory