AirTrunk BOM3 Mumbai is a data center project in Chandivali, Mumbai, India, operated by AirTrunk (formerly Lumina CloudInfra). It is at the land and permitting stage. It is planned for 48 MW of IT load.

Latest change on record: entered the record as land and permitting on 19 September 2025.

Open on the mapSuggest a correction
Stage
Land and permitting
Planned IT load
48 MW
Running now
Not disclosed
Operator
AirTrunk (formerly Lumina CloudInfra)
Colocation
AI workloads
No signal either way
Evidence grade
Corroborated
Will it get built?Open question3 of 7 gates passed
✓ Land secured✓ Power arranged○ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Approvals granted.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How India approves, powers and taxes data centers is on Data center rules in India.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. On record: named funder, three or more sources, dated source in the last 24 months. Criteria.

AI workloads

StatusNo signal either way

No public signal either way.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.

Stage history

2025-09-19Land and permitting · airtrunk.com

Who is behind it

OperatorAirTrunk (formerly Lumina CloudInfra) · Colocation
Funder, EquityBlackstone

Who uses the compute

Checked on 2026-10-02. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

ArusGrid estimate, building costabout US$271m to US$367m

No figure has been announced. This range is 48 MW of planned IT load times a published benchmark of US$6.64 per watt for Mumbai, plus or minus 15 percent. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Colocation price per kW of IT load per month

ArusGrid estimate, grade CINR 7,650 to INR 11,900 (about USD 91 to 142)

ArusGrid estimate, grade C. Published band for this country. Priced on the wholesale band. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, wholesale (2024-12)INR 7,650 to INR 11,900 Cushman & Wakefield for Sify Infinit Spaces, 2025-10-16
Land
Land sellerPrasoon Spaces LLP · 2.04 acres · INR 2,940m · Sep 2025 Reported source ↗
Rs 294 crore, stamp duty Rs 17.64 crore. Buyer Lumina CloudInfra Pvt Ltd, now AirTrunk. Registered 19 Sep 2025.
Land sellerChawla Brothers LLP · 1.75 acres · INR 1,810m · Sep 2025 Reported source ↗
Rs 181 crore, stamp duty Rs 10.86 crore. Buyer Lumina CloudInfra Pvt Ltd, now AirTrunk. Registered 19 Sep 2025. The two parcels total 3.79 acres, close to AirTrunk's 1.5ha.
Power supply
Grid supply33kV · Oct 2026 Confirmed source ↗
The operator page lists a 33kV feed. Page undated, read 2026-10-18.
Water and cooling
Coolingdesign PUE 1.4 Confirmed source ↗
Design PUE below 1.4 per the operator page. Cooling type not stated. Page undated, read 2026-10-18.

Sources

  1. BOM3 Mumbai (AirTrunk)
  2. Blackstone to invest nearly Rs 5,000 crore to develop data centre in MMR (Business Standard, 2025-09-24)
  3. India's Lumina CloudInfra acquires land in Mumbai for 60MW data center (DCD, 2025-09-26)
  4. APAC data center firm AirTrunk enters India, acquires Lumina CloudInfra (DCD, 2026-04-20)
  5. AirTrunk Acquires Lumina CloudInfra (AirTrunk, 2026-04-20)
  6. Blackstone-Backed Lumina Acquires Prime Chandivali Land for ₹475 Crore (The Realty Today, 2025-09-28)

More in Mumbai metro

Also run by AirTrunk

Definitions and sourcing rules · CC BY-NC 4.0 · corrections@arusgrid.com