AirTrunk BOM3 Mumbai is a data center project in Chandivali, Mumbai, India, operated by AirTrunk (formerly Lumina CloudInfra). It is at the land and permitting stage. It is planned for 48 MW of IT load.
Latest change on record: entered the record as land and permitting on 19 September 2025. Record last checked against its sources on 2 October 2026.
Mumbai metro holds 26 active projects with 2,068 MW of planned IT load between them, and AirTrunk BOM3 Mumbai ranks 15th by planned capacity. Of those, 3 are operational, 4 are operational and expanding, 9 are under construction, 7 are at the land and permitting stage and 3 are announced only. Published colocation vacancy in Mumbai metro was 6.6% as of June 2025. Vacancy excludes hyperscaler self-build.
AirTrunk has 3 others in India and 7 projects elsewhere in the dataset tracked by ArusGrid, including AirTrunk MAA1, AirTrunk BOM1 (ex-Lumina Airoli) and AirTrunk Raigad (Pen) campus. Named funding comes from Blackstone on the equity side. No user of the capacity is on the public record as of 2026-10-02, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.
The stage was recorded as at the land and permitting stage on 19 September 2025.
The US export control position for advanced AI chips in India, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 5 public sources for this project, the latest dated 20 April 2026, and last checked the record on 2 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
No public signal either way.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Checked on 2026-10-02. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.
ArusGrid estimate, grade C. Published band for this country. Priced on the wholesale band. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.
All projects in Mumbai metro · All projects in India · All AirTrunk projects · All projects at the land and permitting stage · Full directory