Digital Connexion BOM10 data center

Mumbai (Chandivali), Maharashtra, India · Mumbai metro market · location approximate to district level

Digital Connexion BOM10 is a data center project in Mumbai (Chandivali), India, operated by Digital Connexion. It is under construction. The only published capacity figure is 40 MW of total facility power. IT load will be lower.

Latest change on record: entered the record as under construction on 20 February 2025.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
40 MW
Total facility power
Running now
Not disclosed
Operator
Digital Connexion
Joint venture
AI workloads
No signal either way
Evidence grade
Corroborated
Will it get built?Leaning yes4 of 7 gates passed
✓ Land secured○ Power arranged✓ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How India approves, powers and taxes data centers is on Data center rules in India.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. On record: named funder, dated, sized phase, three or more sources, dated source in the last 24 months. Criteria.

AI workloads

StatusNo signal either way

No public signal either way.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.

Phases

BOM10 · Under construction40 MW, target 2026

Stage history

2025-02-20Under construction · x.com

Who is behind it

OperatorDigital Connexion · Joint venture
Funder, Joint venture partnerReliance Industries
Funder, Joint venture partnerBrookfield Infrastructure
Funder, Joint venture partnerDigital Realty

Who uses the compute

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.

Colocation price per kW of IT load per month

ArusGrid estimate, grade CINR 7,650 to INR 11,900 (about USD 91 to 142)

ArusGrid estimate, grade C. Published band for this country. Priced on the wholesale band. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, wholesale (2024-12)INR 7,650 to INR 11,900 Cushman & Wakefield for Sify Infinit Spaces, 2025-10-16
Land
Site2.15 acres · Jun 2023 Inferred by ArusGrid source ↗
Parcel bought by BAM Digital Realty, the predecessor of Digital Connexion. Seller not named.
Why we think so. The 2.15-acre Chandivali purchase is the only Chandivali parcel the operator or its predecessor has announced, and the operator page gives BOM10 about 2.1 acres.

Sources

  1. Construction Update from Metro Mumbai. Progress continues at BOM10 (Digital Connexion (X), 2025-02-20)
  2. BOM 10 Data Center in Mumbai (Digital Connexion, 2026-10-02)
  3. Data Center Services in Mumbai (Digital Connexion, 2026-10-02)
  4. BAM Digital Realty acquires land in Mumbai for 35MW data center (DatacenterDynamics, 2023-06-13)
  5. Brookfield Digital Realty Partnership Invests 2,000 INR-Crore to Develop Cutting-Edge Data Center in Mumbai (Biltrax Media, 2023-06-14)

More in Mumbai metro

Also run by Digital Connexion

Definitions and sourcing rules · CC BY-NC 4.0 · corrections@arusgrid.com