Sichuan Energy Investment Tianfu Cloud Digital Intelligence Industrial Park (四川能投天府云数智产业园)

Jianyang, Sichuan, China · Tianfu (Chengdu) market · location approximate to city level

Also listed as Tianfu Cloud Data Industry Base (四川能投天府云数据产业基地).

Sichuan Energy Investment Tianfu Cloud Digital Intelligence Industrial Park (四川能投天府云数智产业园) is a data center project in Jianyang, China, operated by Sichuan Tianfu Cloud Data Technology (四川省天府云数据科技有限责任公司), Sichuan Energy Investment Group (四川能投). It is operational. The operator has not published an IT load figure. It is planned for 50,000 racks, with 5,000 in service. ArusGrid does not convert racks into MW.

Latest change on record: moved to operational on 31 October 2023. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Sichuan Tianfu Cloud Data Technology (四川省天府云数据科技有限责任公司), Sichuan Energy Investment Group (四川能投)
energy
AI workloads
Confirmed
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Tianfu (Chengdu) holds 6 active projects with 0 MW of planned IT load between them, and Sichuan Energy Investment Tianfu Cloud Digital Intelligence Industrial Park (四川能投天府云数智产业园) has no published figure so it sits outside that ranking. Of those, 3 are operational, 2 are operational and expanding and 1 is under construction. No third party publishes a colocation vacancy rate for Tianfu (Chengdu), and ArusGrid does not estimate one.

It is the only Sichuan Energy Investment project ArusGrid tracks. It sits on the Tianfu Cloud data industry base, Chengdu Aerospace Industrial Functional Zone (成都空天产业功能区), Jianyang campus. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The build is phased. Phase 1, 5,000 racks is operational with a 2023 target; Later phases, campus total about 50,000 standard racks is announced. The dated record runs from announced only on 30 July 2020 to operational on 31 October 2023. The money on record is CN¥10bn as of May 2024, the announced investment.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 6 public sources for this project, the latest dated 10 May 2024, and last checked the record on 19 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsNo

AI workloads

StatusConfirmed

Hundreds of servers deliver about 4,800P (FP16) of compute. The first 42kW air-cooled AI racks went live in 2024.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Phases

Phase 1, 5,000 racks · OperationalSize not published, target 2023
Later phases, campus total about 50,000 standard racks · AnnouncedSize not published

Stage history

2020-07-30Announced · cbgc.scol.com.cn
2021-06-01Under construction · c.m.163.com
2023-10-31Operational · sichuan.scol.com.cn

Who is behind it

OperatorSichuan Tianfu Cloud Data Technology (四川省天府云数据科技有限责任公司), Sichuan Energy Investment Group (四川能投) · energy

Who uses the compute

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.

Money at this site

Announced investment, 2024-05CN¥10bn

The figure covers the whole campus.

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
Site138,667 sqm · Jun 2023 Reported source ↗
Source states 208 mu for Phase 1; converted at 666.7 sqm per mu. Counterparty not disclosed. Land use rights in China are granted by the state.

Sources checked 2026-10-19

  1. 超级智算 40万台电脑算力集结简阳“云”端 (中国新闻网·四川新闻, 2024-05-10)
  2. 开张!天府云数智产业园转入运营 成功签下首单 (四川在线, 2023-10-31)
  3. 天府数据中心集群再添新成员 四川能投天府云数据产业基地达到接入条件 (四川在线, 2023-06-01)
  4. 四川能投天府云数据产业基地项目一期预计今年年底竣工投产 (成都简阳发布 (网易号), 2022-07-18)
  5. 四川能投天府云数据产业基地(一期)已具备客户接入条件 (人民网四川频道, 2023-05-31)
  6. 四川能投数产公司拟百亿投资 打造西南首个“天府云数据产业园” (川观新闻, 2020-07-30)

More in Tianfu (Chengdu)

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.