ArusGrid tracks 5 active data center projects operated by ByteDance, with 7 MW of planned IT load, across China and Thailand. Of these, 1 is operational and expanding, 2 are at the land and permitting stage and 2 are announced only.
ArusGrid classes the operator as hyperscaler self-build. Projects appear under the names TikTok Pte Ltd (ByteDance), Volcano Engine (火山引擎), permit holder 中卫朔方星河科技有限公司, Volcano Engine (火山引擎), via Wuhu Jiangdong Mingyi Technology (芜湖江东名邑科技有限公司) and Volcano Engine (火山引擎, ByteDance). The largest project is Volcano Engine Zhongwei Xuanhe Computing Centre, Phase 1 at 7.47 MW in Zhongwei, at the land and permitting stage. Disclosed tenants across its projects are ByteDance and ByteDance (own use).
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| Volcano Engine Zhongwei Xuanhe Computing Centre, Phase 1 | Zhongwei | Land and permitting | 7.47 | undisclosed | Volcano Engine (火山引擎), permit holder 中卫朔方星河科技有限公司 | Likely |
| Volcano Engine GW-scale Park, Hohhot | Hohhot | Announced | none published | undisclosed | Volcano Engine (火山引擎, ByteDance) | Likely |
| Volcano Engine GW-scale Computing Center, Ulanqab | Ulanqab | Announced | none published | undisclosed | Volcano Engine (火山引擎, ByteDance) | Likely |
| Volcano Engine YRD Computing Centre (火山引擎长三角算力中心) | Wuhu | Land and permitting | 21,824 racks * | undisclosed | Volcano Engine (火山引擎), via Wuhu Jiangdong Mingyi Technology (芜湖江东名邑科技有限公司) | Likely |
| ByteDance / TikTok Thailand data infrastructure | Bangkok / Samut Prakan / Chachoengsao (multi-site) | Expanding | none published | undisclosed | TikTok Pte Ltd (ByteDance) | Likely |
All operators · Full directory