Also listed as BTC Digital Hai Phong, Trung tâm dữ liệu AI Nam Tràng Cát, Hai Phong, NTC, NTC Digital and Nam Trang Cat.
BTC Digital AI Data Center, Nam Trang Cat IP is a data center project in Hai Phong (Nam Trang Cat Industrial Park, Hai An), Vietnam, operated by BTC Digital Ltd, Nam Trang Cat Investment and Development JSC and SG Partners. It has been announced and has not yet reached the land or permitting stage. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Latest change on record: entered the record as announced on 25 August 2026. Record last checked against its sources on 14 October 2026.
Next gate to watch: Land secured.
Next checkpoint, 25 February 2027. The six-month exclusivity in the MoU ends around this date. If no power deal, investment approval, funder or tenant is on record by then, ArusGrid moves this project to on hold.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Vietnam approves, powers and taxes data centers is on Data center rules in Vietnam.
Hanoi metro holds 6 active projects with 110 MW of planned IT load between them, and BTC Digital AI Data Center, Nam Trang Cat IP has no published figure so it sits outside that ranking. Of those, 3 are operational, 1 is under construction, 1 is at the land and permitting stage and 1 is announced only. No third party publishes a colocation vacancy rate for Hanoi metro, and ArusGrid does not estimate one.
It is the only BTC Digital project ArusGrid tracks. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.
The stage was recorded as announced only on 25 August 2026.
Grid power for a large industrial user in Vietnam costs about US$0.073 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Vietnam, as of 27 September 2026, is recorded as “Licence required as enforced (Country Group D:1), no named authorisation found”. ArusGrid holds 4 public sources for this project, the latest dated 10 September 2026, and last checked the record on 14 October 2026.
One or two hard signals sit behind the announcement. The rules are fixed and published on the Methodology page.
Presented by BTC Digital as an AI data center (AIDC) project.
Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria are published on the Methodology page.
Licence required as enforced (Country Group D:1), no named authorisation found · Licence required as enforced (Country Group D:1), no named authorisation found (2026-09-27) source
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.
No published price band exists for Vietnam, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in Hanoi metro · All projects in Vietnam · All projects announced only · Data center rules in Vietnam · Full directory