Data center projects in Hanoi metro

Vietnam · Southeast Asia · dataset updated 2026-09-27

ArusGrid tracks 5 active data center projects in Hanoi metro, Vietnam, with 110 MW of planned IT load. Of these, 3 are operational, 1 is under construction and 1 is at the land and permitting stage. Projects under construction or commissioning account for 60 MW and operational sites for 30 MW of planned capacity. Operators have disclosed 30 MW actually running, a figure most of them do not publish.

The largest project is Viettel An Khanh Data Center at 60 MW, under construction. The operators with the most planned capacity here are Viettel (90 MW across 2 projects), G-Group (20 MW across 1 project) and Ministry of Public Security (1 project). No third party publishes a colocation vacancy rate for Hanoi metro, and ArusGrid does not estimate one.

Grid power for a large industrial user in Vietnam costs about US$0.073 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Vietnam, as of 27 September 2026, is recorded as “Licence required as enforced (Country Group D:1), no named authorisation found”.

Open the mapPipeline view

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
Viettel An Khanh Data CenterAn Khanh (fmr Hoai Duc)Under construction60undisclosedViettel IDC (Viettel Group)Likely
Viettel IDC Hoa LacHoa LacOperational30 *30Viettel IDC (Viettel Group)Confirmed
G-Campus Hoa Lac (High-Tech & Data Centre Complex)Hoa LacLand and permitting20undisclosedG-Group TechnologyConfirmed
National Data Center No.1Hoa LacOperationalnone publishedundisclosedMinistry of Public Security (National Data Center)No signal either way
VNPT IDC Hoa LacHoa LacOperationalnone publishedundisclosedVNPT (VNPT IDC)Confirmed

Other markets in Vietnam

Operators here with their own page

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.