How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusLikely
256MW modern greenfield ($3bn)
Phases
Building 1 · Under constructionSize not published, target 2025
Full build (10 buildings) · Announced256 MW
Who is behind it
OperatorVantage Data Centers · Colocation
Funder, EquityDigitalBridge
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Money at this site
Announced investment, 2023-05US$3bn
The figure covers the whole campus.
Land
Industrial estateCyberview Sdn Bhd · 35 acres · May 2023 Reported source ↗ Described as land partner; sale or lease not stated
Power supply
Dedicated substationTNB · 500 MVA · 275kV · Aug 2024 Confirmed source ↗ Rooftop solar for offices only
Water and cooling
CoolingClosed-loop cooling Confirmed source ↗ Closed-loop chilled water from air-cooled chillers, near-zero water use claimed
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedSunway Construction Sdn Bhd · Main contractor · RM747.8m (≈US$168m) · Mar 2024 source ↗ This project is one of 4 that fit. The others are Google (Pearl Computing) Elmina Data Centre & Cloud Region, AWS Asia Pacific (Malaysia) Region (3 AZs, Klang Valley), EdgeConneX Cyberjaya Campus.