How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesNo
Dated source in the last 24 monthsNo
AI workloads
StatusNo signal either way
no cooling/density/tenant signal published
Phases
Block 3 · OperationalSize not published, target 2025
Who is behind it
OperatorAIMS Data Centre (TIME dotCom) · Colocation
Funder, EquityTIME dotCom
Funder, EquityDigitalBridge
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Platform deals that include it
DigitalBridge 49% stake in AIMS
Platform acquisition, 2023-12US$500m
Platform capital spans several sites. It is never added to this project's own figure.
Who builds it
Main contractorGamuda Engineering Sdn Bhd · RM500m (≈US$113m) Reported source ↗ AIMS Cyberjaya Block 2 (completed in 8 months, IBS) and Block 3 (started May 2024)
Main contractorBinastra Builders Sdn Bhd · RM250.37m (≈US$56m) · Feb 2025 Reported source ↗ Six-storey data centre, phased completion Jun to Dec 2025
Fit-out contractorBinastra Builders Sdn Bhd · RM188.5m (≈US$42m) · Nov 2025 Reported source ↗ M&E fit-out of same six-storey DC plus guardhouse and refuse room, 4 months