NEXTDC KL1

Petaling Jaya, Selangor, Malaysia · Klang Valley market · location approximate to district level

NEXTDC KL1 is a data center project in Petaling Jaya, Malaysia, operated by NEXTDC. It is operational and expanding. It is planned for 65 MW of IT load. The operator reports 15 MW running.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
65 MW
Running now
15 MW
Operators rarely publish this
Operator
NEXTDC
Colocation
AI workloads
Likely
Evidence grade
Verified

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsNo

AI workloads

StatusLikely

AI-ready marketing; first Uptime Tier IV cert in Peninsular MY; 2026 greenfield by listed AU operator

Phases

Phase 1 · Operational15 MW, target 2026
Phases 2-5 · Announced50 MW

Who is behind it

OperatorNEXTDC · Colocation

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Announced investment, 2026-05A$1,000m (about US$650m)
Who builds it
Main contractorPembinaan Mitrajaya Sdn Bhd · RM375.5m (≈US$85m) · Jan 2025 Reported source ↗
KL1 main works: Stage 1 Ph2, Stage 2, Stage 3 Ph1 (original award)
Main contractorPembinaan Mitrajaya Sdn Bhd · RM426.3m (≈US$96m) · Sep 2025 Reported source ↗
KL1 variation orders adding later phases; contract to RM801.8m, complete Apr 2026
Main contractorPembinaan Mitrajaya Sdn Bhd · RM42.81m (≈US$10m) · Jan 2026 Reported source ↗
Fourth VO, Phase 3 Stage 1; contract to RM844.66m, complete Jul 2026
Piling and earthworksPembinaan Mitrajaya Sdn Bhd · RM54m (≈US$12m) · Mar 2026 Reported source ↗
KL1 Stage 4 early works (ST4-GC01), to Oct 2026

Sources checked 2026-07-12

  1. nextdc.com
  2. datacenterdynamics.com

More in Klang Valley

Also run by NEXTDC

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-26.