Princeton Digital Group JH1

Sedenak (Kulai), Johor, Malaysia · Johor market · location approximate to district level

Princeton Digital Group JH1 is a data center project in Sedenak (Kulai), Malaysia, operated by Princeton Digital Group. It is operational and expanding. It is planned for 150 MW of IT load. The operator reports 52 MW running.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
150 MW
Running now
52 MW
Operators rarely publish this
Operator
Princeton Digital Group
Colocation
AI workloads
Confirmed
Evidence grade
Verified

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsNo

AI workloads

StatusConfirmed

AI-ready campus per operator (150MW)

Phases

Phase 1 (Bldg 1) · Operational52 MW, target 2024
Bldg 3 (topped out late 2025) · Under constructionSize not published

Who is behind it

OperatorPrinceton Digital Group · Colocation
Funder, EquityWarburg Pincus
Funder, EquityOntario Teachers' Pension Plan
Funder, EquityMubadala

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Announced investment, 2024-07US$1.5bn

The figure covers the whole campus.

Land
Land sellerJLand Group Sdn Bhd (Johor Corporation) · 31 acres · May 2023 Confirmed source ↗
Sedenak Tech Park; price undisclosed (RM2bn is Phase 1 investment, not land price)
Power supply
Grid supplyTenaga Nasional Berhad (TNB) · Jul 2024 Confirmed source ↗
ESA covers entire JH1 campus capacity; Phase 1 (52MW) energised via TNB Green Lane Pathway · Applies to the whole campus.
On-site solarPrinceton Digital Group · Jul 2024 Confirmed source ↗
Rooftop solar panels; MW not stated

Sources checked 2026-07-12

  1. princetondg.com
  2. datacenterdynamics.com

More in Johor

Also run by Princeton Digital Group

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-26.