Cikarang, Bekasi, West Java, Indonesia · Greater Jakarta market · location approximate to district level

PDG JC3, GIIC Kota Deltamas is a data center project in Cikarang, Bekasi, Indonesia, operated by Princeton Digital Group. It is under construction. It is planned for 120 MW of IT load.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
120 MW
Running now
0 MW
Operators rarely publish this
Operator
Princeton Digital Group
Colocation
AI workloads
Likely
Evidence grade
Corroborated

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsNo

AI workloads

StatusLikely

PDG describes JC3 as 'flexible design tailored to support both hyperscale and AI infrastructure deployments'; 120MW modern greenfield; May 2026 financing PR says the raise was 'on the back of customer success' implying anchor hyperscale pre-lease.

Phases

Phase 1 (Building 1) · Under constructionSize not published, target 2026
Building 2 · AnnouncedSize not published

Who is behind it

OperatorPrinceton Digital Group · Colocation
Funder, DebtDBS
Funder, DebtHSBC
Funder, DebtMaybank
Funder, DebtSMBC
Funder, DebtStandard Chartered
Client, reported, unconfirmedUndisclosed hyperscaler

Money at this site

Announced investment, 2025-01US$1bn

The figure covers the whole campus.

Platform deals that include it

PDG ~US$856M green financing for JC3
Debt, 2026-05
US$856m

Platform capital spans several sites. It is never added to this project's own figure.

Land
Land sellerPT Puradelta Lestari Tbk (DMAS), GIIC Kota Deltamas · Rp171bn (≈US$11m) · 2024 Inferred by ArusGrid source ↗
Customer-level revenue from PDG in DMAS 2024 reporting
Why we think so. DMAS reported PT Princeton Digital Group as a 2024 land customer at Deltamas; PDG's only Deltamas site bought in 2024 is JC3 (JC4 land was bought in 2026).
Power supply
Dedicated substationPLN · 200 MVA · 150kV · Sep 2026 Reported source ↗
GI 150 kV Sukamahi energized, prepared to supply PDG JC3 up to 200 MVA

Sources checked 2026-09-11

  1. princetondg.com
  2. princetondg.com
  3. princetondg.com

More in Greater Jakarta

Also run by Princeton Digital Group

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-26.