Stage
Under construction
Planned IT load
62 MW
Running now
Not disclosed
Operators rarely publish this
Operator
AirTrunk (Lumina CloudInfra)
Colocation
AI workloads
Likely
Evidence grade
Corroborated

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

AirTrunk markets the India platform as AI-ready high-density campuses; Lumina said in 2023 it was in talks with Microsoft, Amazon, Google and Oracle, none confirmed.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Phase 1 · Under constructionSize not published, target 2025
Phase 2 · AnnouncedSize not published

Stage history

2023-05-24Under construction · datacenterdynamics.com

Who is behind it

OperatorAirTrunk (Lumina CloudInfra) · Colocation
Funder, EquityBlackstone

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Announced investment, 2023-05US$300m

The figure covers the whole campus.

Platform deals that include it

AirTrunk acquires Lumina CloudInfra (Blackstone), ~600MW planned across Mumbai, Chennai, Hyderabad
Platform acquisition, 2026-04-20
Not disclosed

Platform capital spans several sites. It is never added to this project's own figure.

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-09-27

  1. Blackstone-backed Lumina CloudInfra breaks ground on 60MW data center campus in Navi Mumbai, India (DCD, 2023-05-24)
  2. BOM1 Mumbai | AirTrunk (AirTrunk (operator site, accessed), 2026-09-27)
  3. AirTrunk Acquires Lumina CloudInfra (AirTrunk, 2026-04-20)

More in Mumbai metro

Also run by AirTrunk

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-27.