CapitaLand Data Centre Navi Mumbai

Navi Mumbai, Maharashtra, India · Mumbai metro market · location approximate to district level

CapitaLand Data Centre Navi Mumbai is a data center project in Navi Mumbai, India, operated by CapitaLand India. It is operational and expanding. It is planned for 71 MW of IT load. The operator reports 34 MW running.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
71 MW
Running now
34 MW
Operators rarely publish this
Operator
CapitaLand India
Colocation
AI workloads
No signal either way
Evidence grade
Verified

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsYes

AI workloads

StatusNo signal either way

No public signal either way.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Tower 1 · Operational34 MW, target 2025
Tower 2 · Under construction37 MW

Stage history

2025-08-12Operational · mti.gov.sg
2026-01-02Expanding · dcnnmagazine.com

Who is behind it

OperatorCapitaLand India · Colocation
Funder, EquityCapitaLand India Trust
Funder, EquityCapitaLand India Data Centre Fund

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Platform deals that include it

CapitaLand MoU with Maharashtra, US$2.2bn over five years
Other, 2025-08-12
US$2.2bn

Platform capital spans several sites. It is never added to this project's own figure.

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-09-27

  1. CapitaLand India Trust divests data centre stakes (DCNN, 2026-01-02)
  2. Remarks by Deputy Prime Minister and Minister for Trade and Industry Gan Kim Yong at the Opening of CapitaLand's Data Centre in Navi Mumbai (Singapore MTI, 2025-08-12)

More in Mumbai metro

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-27.