PDG MU1 campus

Navi Mumbai, Maharashtra, India · Mumbai metro market · location approximate to district level

PDG MU1 campus is a data center project in Navi Mumbai, India, operated by Princeton Digital Group. It is operational and expanding. It is planned for 150 MW of IT load. The operator reports 50 MW running.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
150 MW
Running now
50 MW
Operators rarely publish this
Operator
Princeton Digital Group
Colocation
AI workloads
Likely
Evidence grade
Verified

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Campus above 100MW with a 2026 expansion phase; PDG markets AI-ready capacity.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Buildings 1 and 2 · Operational50 MW, target 2025
Expansion phase 1 (to five buildings) · Under construction100 MW

Stage history

2022-12-31Operational · datacenterdynamics.com
2026-04-10Expanding · datacenterdynamics.com

Who is behind it

OperatorPrinceton Digital Group · Colocation
Funder, EquityWarburg Pincus
Funder, EquityOntario Teachers' Pension Plan
Funder, EquityMubadala
Funder, EquityStonepeak

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-09-27

  1. PDG breaks ground on latest Mumbai data center (DCD, 2026-04-10)

More in Mumbai metro

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-27.