How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsNo
AI workloads
StatusLikely
Hyperscaler self-build; Microsoft describes Indonesia Central as 'hyperscale infrastructure built to support growth in AI'; Azure OpenAI services being brought in-region.
Phases
Phase 1 (Indonesia Central region live) · OperationalSize not published, target 2025
Who is behind it
OperatorMicrosoft · Hyperscaler self-build
Funder, EquityMicrosoft
Client, confirmedMicrosoft (own use)
Platform deals that include it
Microsoft US$1.7B Indonesia cloud & AI investment (2024 to 2028)
Country programme, 2024-04US$1.7bn
Platform capital spans several sites. It is never added to this project's own figure.
Land
Land sellerPT Puradelta Lestari Tbk (DMAS), Kota Deltamas / GIIC · Rp810bn (≈US$51m) · 2024 Reported source ↗ Buyer PT Microsoft Operations Indonesia; customer-level revenue in DMAS reporting
Power supply
Dedicated substationPLN (UIP JBT / Pusmanpro) · 150kV · Apr 2026 Reported source ↗ GI 150 kV Data Center Bay Microsoft, lines JKT 11 A & B at GIIC Deltamas completed; no MVA disclosed
Water and cooling
WaterIndustrial raw water · GIIC industrial estate (Kawasan Industri GIIC); KIIC also named for other sites Inferred by ArusGrid source ↗ Why we think so. Fact sheet names GIIC (Cikarang) as a water source; our Microsoft Cikarang entry is the only Microsoft site that fits GIIC.
CoolingEvaporative cooling Inferred by ArusGrid source ↗ Indirect evaporative cooling, water-cooled chillers in warmer periods (Indonesia region)