Data center projects in Batam and Bintan

Indonesia · Southeast Asia · dataset updated 2026-09-27

ArusGrid tracks 12 active data center projects in Batam and Bintan, Indonesia, with 835 MW of planned IT load. Of these, 3 are operational and expanding, 4 are under construction, 2 are at the land and permitting stage and 3 are announced only. Projects under construction or commissioning account for 523 MW and operational sites for 217 MW of planned capacity. Operators have disclosed 63 MW actually running, a figure most of them do not publish.

The largest project is DayOne Kabil Industrial Tech Park (KITP) at 360 MW, under construction. The operators with the most planned capacity here are DayOne (432 MW across 2 projects), BW Digital (120 MW across 1 project) and Princeton Digital Group (96 MW across 1 project). No third party publishes a colocation vacancy rate for Batam and Bintan, and ArusGrid does not estimate one.

Grid power for a large industrial user in Indonesia costs about US$0.062 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Indonesia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”.

Open the mapPipeline view

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
DayOne Kabil Industrial Tech Park (KITP)BatamUnder construction360undisclosedDayOne (PT Digitalland Service One)Confirmed
BW Digital NDP1BatamExpanding12024BW DigitalConfirmed
Princeton Digital Group BT1BatamUnder construction96undisclosedPrinceton Digital GroupLikely
Racks Central Batam (RCBI)BatamLand and permitting95undisclosedRacks CentralLikely
DayOne Nongsa Digital Park Campus (NDP1-3)BatamExpanding7234DayOne (PT Digitalland Service One)Likely
NeutraDC Nxera Batam BTM-1BatamUnder construction51undisclosedNeutraDC Nxera BatamConfirmed
Golden Digital Gateway (Nongsa One)BatamExpanding255.2Golden Digital Gateway (Data Center First)No signal either way
AESLER-GREENIX Mark 1BatamUnder construction16undisclosedPT Aesler Grup Internasional TbkNo signal either way
Altiva Identity Datacenter NongsaBatam (Nongsa)Announcednone publishedundisclosedPT Altiva Identity DatacenterNo signal either way
DCI Bintan Campus (Hyperscale 3 / H3)BintanLand and permittingnone publishedundisclosedDCI IndonesiaLikely
Quantum AI Data Center (WorldVuer iByond)BatamAnnouncednone publishedundisclosedWorldVuer iByondNo signal either way
Range IDC / Equator Gate System Batam AI Data CenterBatamAnnouncednone publishedundisclosedEquator Gate System Batam (EGSB) / Range Intelligent ComputingLikely

Cancelled

ProjectCityStagePlanned MWRunning MWOperatorAI
Pusat Data Nasional 2 (National Data Center Batam)BatamCancellednone publishedundisclosedKementerian Komunikasi dan Digital (Komdigi)No signal either way

Other markets in Indonesia

Operators here with their own page

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.