How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsNo
AI workloads
StatusNo signal either way
No public signal either way.
Phases
Phase 1 · Operational5.2 MW, target 2025
Phase 2 · Under construction20 MW, target 2026
Who is behind it
OperatorGolden Digital Gateway (Data Center First) · Joint venture
Funder, EquityGaw Capital Partners
Funder, Joint venture partnerSinar Primera
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Land
Industrial estateCitramas Group (Nongsa Digital Park) · 25,700 sqm · Oct 2021 Reported source ↗ Nongsa One site of 276,600 sq ft in Nongsa Digital Park.
Power supply
Grid supplyPLN · Oct 2021 Reported source ↗ Dual feeds from two independent PLN substations, with capacity reserved for expansion.