ArusGridProject
Directory › Indonesia › Batam and Bintan › BW Digital NDP1

BW Digital NDP1 data center

Batam, Riau Islands, Indonesia · Batam and Bintan market · location approximate to district level

BW Digital NDP1 is a data center project in Batam, Indonesia, operated by BW Digital. It is under construction. It is planned for 120 MW of IT load.

Latest change on record: entered the record as under construction on 12 February 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
120 MW
Running now
Not disclosed
Operator
BW Digital
Colocation
AI workloads
Confirmed
Evidence grade
Corroborated
Will it get built?Leaning yes5 of 7 gates passed
✓ Land secured○ Power arranged✓ Approvals granted✓ Money committed○ Tenant or own use✓ Builder appointed✓ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Indonesia approves, powers and taxes data centers is on Data center rules in Indonesia.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. On record: named funder, dated, sized phase, three or more sources, dated source in the last 24 months. Criteria.

AI workloads

StatusConfirmed

Operator states NDP1 is built to Nvidia AI-factory guidelines and supports up to 140kW racks with direct liquid cooling (direct-to-chip or immersion); 20-40kW air-cooled baseline; 7m slab-to-slab, 20kN/m2 floor loading.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.

Phases

Phase 1 · Under construction24 MW, target 2026

Stage history

2026-02-12Under construction · bw-digital.com

Who is behind it

OperatorBW Digital · Colocation
Funder, EquityBW Group

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

ArusGrid estimate, building costabout US$1.1bn to US$1.7bn

No figure has been announced. This range is 120 MW of planned IT load times a published benchmark of US$11.21 per watt for Jakarta, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Project team
Mechanical and electrical worksSchneider Electric · Apr 2025 Confirmed source ↗
Strategic technology partner supplying an extensive Schneider Electric solution for NDP1. Systems not itemised.
Land
Land sellerCitramas Group (Nongsa Digital Park) · 55,000 sqm · Mar 2024 Reported source ↗
More than 55,000 sqm acquired from Citramas. Tenure not disclosed.
Power supply
Power allocation or plannot named · Oct 2025 Reported source ↗
20-year PPA in force since 2024. Counterparty and source not stated. · Reported in coverage of the NDP1 topping out at Nongsa Digital Park. · Applies to the whole campus.
Water and cooling
CoolingEvaporative cooling Reported source ↗
Rooftop cooling towers installed on NDP1 first module

Sources

  1. bw-digital.com
  2. datacentermap.com
  3. datacenterdynamics.com
  4. baxtel.com
  5. BW Digital – February Update on Batam DC project NDP1 (BW Digital, 2026-02-12)
  6. TelkomGroup dan Mitra Berhasil Daratkan Kabel Laut NCC di Batam, Perkuat Konektivitas Digital (Republika, 2026-07-22)
  7. Lampaui Nasional, Industri Pusat Data di Batam Tumbuh 22% per Tahun (Fortune Indonesia, 2026-07-20)
  8. BW Digital tops off data center in Batam, Indonesia (DCD, 2025-10-10)
  9. Form F-1 Registration Statement, DayOne Data Centers Ltd (US SEC (EDGAR), 2026-10-05)
  10. Airlangga Resmikan Kabel Bawah Laut Nongsa-Changi, Perkuat Koridor Digital RI-Singapura (Investortrust, 2026-07-20)
  11. Insiden Listrik Padam di Batam, PLN: Industri Data Center Ikut Terdampak (Bisnis, 2026-10-13)

Same campus, Nongsa Digital Park

More in Batam and Bintan