Also listed as DayOne Kabil Industrial Tech Park and Kabil Industrial Tech Park.
DayOne Kabil Industrial Tech Park (KITP) is a data center project in Batam, Indonesia, operated by DayOne (PT Digitalland Service One). It is under construction. It is planned for 360 MW of IT load.
Next gate to watch: Money committed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Indonesia approves, powers and taxes data centers is on Data center rules in Indonesia.
Construction or financing is evidenced, or several independent signals agree. On record: disclosed client (confirmed), three or more sources, dated source in the last 24 months. Criteria.
Firmus to deploy a 170,000-GPU cluster here (Grace Blackwell / Vera Rubin / Vera AI), rolling out through 2027-2028 under an Nvidia agreement running to 2034 (DCD, 29 Jun 2026).
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.
360 MW · Full 360MW campus, up to 170,000 Nvidia accelerators, co-developed with DayOne · as of 2026-06-29
Firmus's own release says it will build a 360MW, 170,000-GPU AI factory campus in Batam with DayOne; DCD places it at Kabil Tech Park under the 450MW PLN PPA. No Firmus customer is named for Batam. Meta signed to lease Firmus Southeast Asia capacity (DCD, 29 Sep 2026) without a site named, held as a lead.
Source · Firmus to Build 170,000 GPU AI Factory Campus with NVIDIA for Global AI-Natives (Firmus Technologies, 2026-06-29)
Source · Firmus to deploy 170,000 GPU cluster in Batam, Indonesia (DCD, 2026-06-29)
No figure has been announced. This range is 360 MW of planned IT load times a published benchmark of US$11.21 per watt for Jakarta, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.
Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.
Platform capital spans several sites. It is never added to this project's own figure.
All projects in Batam and Bintan · All projects in Indonesia · All DayOne projects · All projects under construction · Data center rules in Indonesia · Full directory