ArusGridProject
Directory › Thailand › NTT Bangkok 2 & 3 (Amata City Chonburi)

NTT Bangkok 2 & 3 (Amata City Chonburi)

Amata City Chonburi Industrial Estate, Chonburi, Thailand · EEC (Eastern Seaboard) market · location approximate to district level

NTT Bangkok 2 & 3 (Amata City Chonburi) is a data center project in Amata City Chonburi Industrial Estate, Thailand, operated by NTT Global Data Centers. It is operational. The operator has not published a capacity figure, and ArusGrid does not estimate one. The operator reports 5 MW running.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
Not published
Running now
5 MW
Operators rarely publish this
Operator
NTT Global Data Centers
Colocation
AI workloads
No signal either way
Evidence grade
Verified
Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsNo

AI workloads

StatusNo signal either way

No public signal either way.

Phases

BKK3 · Operational12 MW, target 2025

Who is behind it

OperatorNTT Global Data Centers · Colocation
Funder, EquityNTT

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Land
LandlordAmata Corporation PCL (Amata City Chonburi) · leased · Mar 2023 Confirmed source ↗
Land lease agreement for BKK3, adjacent to BKK2; area not disclosed
Power supply
Power allocation or planAmata B.Grimm Power (B.Grimm Power PCL) · Jan 2026 Confirmed source ↗
B.Grimm states Amata B.Grimm Power has supplied electricity to NTT's second and third data centres.

Sources checked 2026-09-11

  1. services.global.ntt
  2. datacentermap.com
  3. services.global.ntt

Same campus, NTT Amata City Chonburi

More in EEC (Eastern Seaboard)

Also run by NTT GDC

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-26.