ArusGrid tracks 2 active data center projects operated by NTT GDC in Malaysia, with 290 MW of planned IT load. Of these, 1 is operational and 1 is at the land and permitting stage.

Its Malaysia projects sit in Johor and Klang Valley. The largest is NTT Johor Bahru Campus at 290 MW, at the land and permitting stage. Outside Malaysia, NTT GDC has 4 active projects on record in Thailand and Indonesia.

Open the mapPipeline view

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
NTT Johor Bahru CampusGelang PatahLand and permitting290undisclosedNTT DATA / NTT GDCConfirmed
NTT GDC Cyberjaya Campus (CBJ1-CBJ6)CyberjayaOperationalnone publishedundisclosedNTT Global Data CentersNo signal either way

Markets

NTT GDC in other countries

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.