ArusGridOperator
Directory › Operators › ICS Arabia

ICS Arabia data center projects

Saudi Arabia · dataset updated 2026-10-18

ArusGrid tracks 2 active data center projects operated by ICS Arabia, with 115 MW of planned IT load, across Saudi Arabia. Of these, 1 is under construction and 1 is announced only. Projects under construction or commissioning account for 65 MW.

ArusGrid classes the operator as colocation. Projects appear under the names ICS Arabia (with Lumaotong Group and China Mobile International). The largest project is ICS Arabia Desert Dragon (Riyadh phase) at 65 MW in Riyadh, under construction. Named funders across its projects are Lumaotong Group and China Mobile International. Disclosed tenants across its projects are XDS Datacentres.

Open the mapRelationship graph

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
ICS Arabia Desert Dragon (Riyadh phase)Al KharjUnder construction65undisclosedICS ArabiaLikely
ICS Arabia Desert Dragon (Jeddah phase)JeddahAnnounced50 *undisclosedICS Arabia (with Lumaotong Group and China Mobile International)No signal either way

Markets where it builds

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. This page is generated from the dataset, so it cannot drift from the map.