Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.
The figure covers the whole campus.
Platform capital spans several sites. It is never added to this project's own figure.
Project team
Civil and structural worksChina Construction Third Engineering Bureau No.1 Co (CSCEC 3rd Bureau First Co) · Mar 2026 Inferred by ArusGrid source ↗ New-build data centre, civil works general contracting
Why we think so. Source names owner GALAXY PEAK; BOI approval lists Galaxy Peak Data Center Co., Ltd. in Rayong (160MW), part of the Galaxy campus at Silicon Tech Park.
Land
Industrial estateSilicon Tech Park Co., Ltd. (Silicon Tech Park, Ban Chang District, Rayong) · Aug 2025 Reported source ↗ Site is Silicon Tech Park in Ban Chang (EECtp area); area and tenure not disclosed
Power supply
'A photovoltaic power plant will also be developed at the site.' · Grid utility/substation not disclosed · Applies to the whole campus.
On-site solarGalaxy Data Center with Silicon Tech Park · Aug 2025 Reported source ↗ A photovoltaic power plant is planned at the site alongside the data centre. · Planned, no capacity given. · Applies to the whole campus.
Grid supplyProvincial Electricity Authority (PEA) · 230 MW · Oct 2026 Reported source ↗ Galaxy says it will use renewable energy but gives no detail. · Phase 1 will draw 230MW. Galaxy says it connects directly to the PEA grid.
Water and cooling
WaterIndustrial raw water · Private raw-water suppliers (unnamed) Reported source ↗ Approx. 65% of water is raw water from private suppliers; remaining ~35% is treated municipal tap water (see separate fact). Operator says WUE will be publicly disclosed.
Article cites 'Liquid Cooling technology'; exact type not specified
WaterMains drinking water · Provincial Waterworks Authority (PWA), Ban Chang Branch Reported source ↗ Approx. 35% treated municipal tap water; project contributed over THB 37 million to PWA Ban Chang Branch for supply upgrades and dedicated pipelines.
Liquid cooling cited
WaterMains drinking water · Provincial Waterworks Authority (PWA), Ban Chang Branch Reported source ↗ Planned supply is about 35% PWA tap water and 65% raw water from a private supplier, with a dry season backup plan. The developer is funding over 37 million baht for PWA Ban Chang to extend distribution and lay pipes to the site. It says it will disclose actual water use and WUE.
Described only as liquid cooling with water recycling.
WaterIndustrial raw water · Private raw-water suppliers (about 65%) and PWA Ban Chang tap water (about 35%) Reported source ↗ The project gave more than THB37 million to PWA Ban Chang to upgrade water distribution and lay a supply pipe to the site. It has a dry season backup plan and says it will publish actual water use and WUE.
The developer says it uses liquid cooling and recirculates water for reuse.
WaterMains drinking water · Provincial Waterworks Authority (PWA), Ban Chang Branch Reported source ↗ Galaxy Data Center Co., Ltd. says it gave more than THB 37 million to the PWA Ban Chang branch to upgrade water distribution and lay pipes to the site. It says it will publish actual water use and its WUE.
The developer describes liquid cooling with water recirculated for reuse. The exact liquid cooling type is not stated.
WaterMains drinking water · Provincial Waterworks Authority (PWA), Ban Chang Branch · 5,000 m³ a day Reported source ↗ The PWA Ban Chang branch manager said Galaxy applied for 7,000 m3 per day and was approved for 5,000 m3 per day.
CoolingDirect liquid cooling Reported source ↗ Closed-loop liquid cooling sends chilled water directly to the chips.
WaterMains drinking water · Provincial Waterworks Authority (PWA), Ban Chang Branch · 5,000 m³ a day Reported source ↗ The PWA Ban Chang branch manager said the data centre asked for 7,000 m3 of water a day and was approved for 5,000 m3 a day. Galaxy says PWA tap water is about 35% of its supply and private suppliers provide the other 65%.
CoolingDirect liquid cooling Reported source ↗ Closed-loop liquid cooling with chilled water taken direct to the chips, as described by Galaxy at the Ban Chang Talks forum.