SUPERNAP Thailand (Chonburi) data center

Bo Win, Si Racha (Hemaraj Chonburi IE), Chonburi, Thailand · EEC (Eastern Seaboard) market · location approximate to district level

SUPERNAP Thailand (Chonburi) is a data center project in Bo Win, Si Racha (Hemaraj Chonburi IE), Thailand, operated by SUPERNAP (Thailand). It is operational. It is planned for 60 MW of IT load.

Latest change on record: moved to operational on 13 September 2017.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
60 MW
Running now
Not disclosed
Operator
SUPERNAP (Thailand)
Colocation
AI workloads
Unlikely
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Thailand approves, powers and taxes data centers is on Data center rules in Thailand.

Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

How well evidenced is it

Running capacity. The site is operational or expanding. On record: named funder, three or more sources. Criteria.

AI workloads

StatusUnlikely

2017 design era, Tier IV enterprise/interconnection colo with target PUE 1.35-1.45; no liquid-cooling or high-density disclosure.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria.

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Stage history

2016-01-27Under construction · datacenterdynamics.com
2017-09-13Operational · datacenterdynamics.com

Who is behind it

OperatorSUPERNAP (Thailand) · Colocation
Funder, EquityChina Mobile

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Platform deals that include it

China Mobile acquisition of SUPERNAP Thailand
Platform acquisition, 2025-03
Not disclosed

Platform capital spans several sites. It is never added to this project's own figure.

Project team
Main contractorThai Obayashi Corporation · completed Confirmed source ↗
SUPERNAP Thailand data centre (pre-2021, completed 2017)
Land
Industrial estateHemaraj Chonburi Industrial Estate · 12 ha · Jan 2016 Reported source ↗
Site of nearly 12 hectares.
Power supply
Dedicated substation115kV · Sep 2017 Reported source ↗
Power arrives over diverse 115kV transmission paths into two on-site substations.
On-site solarWHA Utilities and Power (WHAUP) · Apr 2022 Reported source ↗
Solar farm of about 10,000 sqm on SUPERNAP-owned land next to the data centre. WHAUP builds it and runs operation and maintenance for 20 years. Investment about THB 30 million. MWp not stated. · PPA signed April 2022. W.Media (2023-01-03) reports the solar farm was built near the facility on a turnkey basis. · Applies to the whole campus.
Water and cooling
Cooling Reported source ↗
Target PUE of 1.35 to 1.45 at opening.

Sources

  1. datacentermap.com
  2. supernap.co.th
  3. baxtel.com
  4. app.mergerlinks.com
  5. Construction begins on SuperNAP Thailand (DatacenterDynamics, 2016-01-27)
  6. SuperNAP International opens Chonburi, Thailand data center (DatacenterDynamics, 2017-09-13)
  7. Supernap Thailand signs PPA to build solar plant (DCD, 2022-04-21)
  8. Supernap opens new data center, a step towards Thailand 4.0 vision (DataCenterNews Asia, 2017-09-14)
  9. US$300M SUPERNAP Thailand Aims to be First Tier IV Gold Data Center In Asia (Converge Digest, 2016-01-14)
  10. WHAUP และ Supernap ฤกษ์ดี เปิด Solar Farm พลังงานหมุนเวียน (Prachachat, 2022-12-15)
  11. บริษัทโทรคมนาคมแห่งชาติฯ ผนึก ซุปเปอร์แนป ยกระดับบริการด้าต้าเซ็นเตอร์ (Thansettakij, 2021-12-09)

More in EEC (Eastern Seaboard)

Also run by China Mobile Intl

Definitions and sourcing rules · CC BY-NC 4.0 · corrections@arusgrid.com