How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsNo
AI workloads
StatusNo signal either way
No public signal either way.
Phases
Buildings A-D (4 x 6MW) · Under construction24 MW, target 2025
Who is behind it
OperatorDC POWER BN1 Co., Ltd. · Joint venture
Funder, Joint venture partnerSTECON Power (STECON Group)
Funder, Joint venture partnerSITEM Corporation
Funder, Joint venture partnerMyTelehaus
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.
Money at this site
Announced investment, 2023-10THB 8bn (about US$219m)
Who builds it
Design and build contractorSino-Thai Engineering and Construction PCL (STECON) · Oct 2023 Reported source ↗ Engineering and construction of four DC buildings, phases C and D first