Meeza M-VAULT 6, 7 and 8 data center

Doha, Qatar · Doha market · location approximate to city level

Meeza M-VAULT 6, 7 and 8 is a data center project in Doha, Qatar, operated by Meeza QSTP LLC. It is under construction. It is planned for 44 MW of IT load.

Latest change on record: moved to financing closed on 29 July 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
44 MW
Running now
Not disclosed
Operator
Meeza QSTP LLC
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured○ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Qatar approves, powers and taxes data centers is on Data center rules in Qatar.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. On record: named funder, disclosed client (confirmed), committed or approved capital, three or more sources, dated source in the last 24 months. Criteria.

AI workloads

StatusLikely

Meeza states the campus is designed for cloud and AI workloads and has signed 6MW (2025 to 10) and 8MW (2026 to 09) leases with an unnamed hyperscaler for AI and cloud workloads. Microsoft is the only hyperscaler publicly hosted by Meeza (M-VAULT 4), so Microsoft is the likely counterparty, unproven.

Access to AI chips

GradeNo public signal

Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria.

Licence required as enforced (Country Group D:4), no named authorisation found · Licence required as enforced (Country Group D:4), no named authorisation found (2026-09-27) source

Phases

Phase 1 (6MW hyperscaler tranche) · Financing closed6 MW
M-VAULT 6, 7, 8 combined · Financing closed44 MW

Stage history

2025-10-28Announced · meeza.net
2026-02Under construction · meeza.net
2026-07-29Financing closed · meeza.net

Who is behind it

OperatorMeeza QSTP LLC · Colocation
Funder, DebtDukhan Bank
Funder, EquityMeeza

Who uses the compute

Tenant · hyperscalerUnnamed global hyperscaler · confirmed

14 MW · 6MW initial phase at M-VAULT 6 (QAR 750m, Oct 2025) plus an 8MW long-term lease at the upcoming campus (QAR 1bn+, Sep 2026); 'one of the world's fastest-growing Cloud Service providers' · as of 2026-09-07

Meeza's own release (QSE-listed issuer) announces an 8MW long-term leasing agreement worth over QAR 1bn with a global hyperscaler, its largest contract, at the upcoming campus. DCD's Oct 2025 piece on the earlier QAR 750m contract places the 6MW first phase in MV6 with later phases taking the campus to 44MW. Same customer description in both.

Source · MEEZA Signs One of the Largest Agreements in the IT Sector, Worth Over QAR 1 Billion. (MEEZA, 2026-09-07)

Source · Qatar's Meeza signs 6MW hosting deal with unnamed hyperscaler (DCD, 2025-10-30)

TenantQai · confirmed

GPU hosting partnership to host advanced GPU infrastructure in M-VAULT 8 · as of 2026-10-29

Meeza Q3 2026 deck lists a Qai GPU Hosting Partnership to host advanced GPU infrastructure in MV8. No MW or contract value is given for it.

Source · MZA Earnings Presentation 29 Oct 2026 (MEEZA QSTP LLC, 2026-10-29)

Money at this site

Debt raised, 2026-07QAR 1.6bn (about US$440m)

This is the size of a loan. ArusGrid excludes it from capital spending totals.

The figure covers several facilities.

Project team
Design and build contractorElegancia Contracting and Industries · QAR 500m (≈US$137m) · Sep 2026 Reported source ↗
Site preparation, construction, MEP, ICT, security, fire protection, controls, testing and handover of one M-VAULT building in two phases

Sources

  1. MEEZA Signs New Landmark Data Centre agreement worth over QAR 750 million to secure 6 megawatts of data center services for a Global hyperscaler (Meeza, 2025-10-28)
  2. MEEZA Secures Additional QAR 1.6 Billion Murabaha Facility to Fund Expansion of Data Centre Capacity to More than Triple Current Size (Meeza, 2026-07-30)
  3. Meeza secures loan facility from Dukhan Bank to fund 44MW build-out (DCD, 2026-08-05)
  4. Qatar's Meeza signs 8MW lease with global hyperscaler (DCD, 2026-09-07)
  5. Estithmar Holding wins QAR500M-plus MEEZA data-centre contract (Mugglehead (relaying Estithmar corporate statement), 2026-09-24)
  6. MEEZA Awards Construction Contract for New Data Center to Elegancia for Over QAR 500 Million (Qatar News Agency, 2026-09-24)
  7. Estithmar wins $137m contract for MEEZA data centre in Qatar (World Construction Network, 2026-09-28)
  8. MEEZA achieves 10.1% Net Profit growth during 2025 and Board of Directors recommends cash dividend (MEEZA, 2026-02-23)
  9. MZA Earnings Presentation Q2 2026 28 Jul 2026 FINAL 1 (MEEZA, 2026-07-28)
  10. Transcript Only Meeza H1 2026 Results Call Jul 28 2026 0300 PM Transcript (MEEZA, 2026-07-28)
  11. MZA Earnings Presentation 29 Oct 2026 (MEEZA QSTP LLC, 2026-10-29)
  12. Meeza's Third Quarter 2026 Financial Results Call (MEEZA QSTP-LLC, 2026-11-02)