ArusGridProject
Directory › India › NCR › Yotta D2

Yotta D2 data center

Greater Noida, Uttar Pradesh, India · NCR market · location approximate to district level

Yotta D2 is a data center project in Greater Noida, India, operated by Yotta Data Services. It is under construction. It is planned for 60 MW of IT load.

Latest change on record: entered the record as under construction on 31 October 2022.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
60 MW
Running now
Not disclosed
Operator
Yotta Data Services
Colocation
AI workloads
Confirmed
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Builder appointed.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How India approves, powers and taxes data centers is on Data center rules in India.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. On record: named funder, disclosed client (confirmed), committed or approved capital, dated, sized phase, three or more sources, dated source in the last 24 months. Criteria.

AI workloads

StatusConfirmed

Operator release 2026 to 02 to 18, 20,736 liquid-cooled Nvidia Blackwell Ultra (B300) GPUs to be installed at D2 in a 60MW deployment.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.

Phases

D2 B300 supercluster · Under construction60 MW, target 2026

Stage history

2022-10-31Under construction · yotta.com

Who is behind it

OperatorYotta Data Services · Colocation
Funder, EquityHiranandani Group

Who uses the compute

Runs compute here · GPU cloudNvidia DGX Cloud · confirmed

60 MW · Four-year engagement valued over US$1bn on a 20,736 Blackwell Ultra B300 supercluster at D2 · as of 2026-02-18

Yotta's release places the 20,736 liquid-cooled B300 GPUs at D2 Greater Noida (60MW) and names Nvidia DGX Cloud as a four-year customer of the cluster; Nvidia's own blog corroborates the deployment at Greater Noida.

Source · Yotta to Deploy One of Asia's Largest NVIDIA Blackwell HGX B300 Superclusters with Over 20,000 NVIDIA Blackwell Ultra GPUs (Yotta Data Services, 2026-02-18)

Source · India Fuels Its AI Mission With NVIDIA (Nvidia blog, 2026-02-18)

Runs compute here · governmentIndiaAI Mission · reported, unconfirmed

Allocation of over 10,000 B300 GPUs from the D2 supercluster · as of 2026-02-18

Yotta's release states over 10,000 of the D2 B300 GPUs are allocated to the IndiaAI Mission. Stated by the operator and Nvidia with no IndiaAI document, so it stays reported.

Source · Yotta to Deploy One of Asia's Largest NVIDIA Blackwell HGX B300 Superclusters with Over 20,000 NVIDIA Blackwell Ultra GPUs (Yotta Data Services, 2026-02-18)

Money at this site

Announced investment, 2026-02US$2bn

It includes GPUs and IT hardware, so it is not comparable with building cost.

Platform deals that include it

Nvidia DGX Cloud engagement at Yotta D2, over US$1bn over four years
Anchor lease, 2026-02-18
US$1.0bn
Yotta Rs 39,000 crore MoU with Uttar Pradesh over 5 to 7 years
Country programme, 2022-10-31
US$4.8bn

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

ArusGrid estimate, grade CINR 6,800 to INR 8,900 (about USD 81 to 106)

ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, hyperscale (2024-12)INR 6,800 to INR 8,900 Cushman & Wakefield for Sify Infinit Spaces, 2025-10-16
Project team
Engineering consultantGrune Designs Pvt Ltd · Nov 2024 Reported source ↗
Electrical engineering consultant for the Yotta Greater Noida data centre park (D1/D2 buildings)
Engineering consultantN K Jain Consulting Engineers · Nov 2024 Reported source ↗
Electrical engineering consultant for the Yotta Greater Noida data centre park (D1/D2 buildings)
Land
Site20 acres · leasehold · Nov 2021 Confirmed source ↗
Area is the whole Greater Noida data centre park. The share for D2 is not stated. The Nidar Infrastructure prospectus (SEC 424B3, 6 Nov 2025) says the campus land is leasehold, with the lease running to 2111. Lenders hold an equitable mortgage on the leasehold rights under D2 and its DG2 building.
Power supply
Dedicated substationUttar Pradesh grid · 220kV · Nov 2021 Confirmed source ↗
Redundant 220kV express feeders into an on-site substation for the Greater Noida park, which the operator sizes at over 250MW of power. · Applies to the whole campus.
Water and cooling
CoolingDirect liquid cooling Confirmed source ↗
Yotta says the 20,736 Blackwell Ultra GPUs to be deployed at D2 are liquid-cooled and the supercluster includes advanced liquid-cooling systems. Facility-level cooling is not described.

Sources

  1. Yotta to deploy NVIDIA Blackwell HGX B300 Superclusters (Yotta, 2026-02-18)
  2. India's Yotta Plans 80,000 Vera Rubin GPUs; World Leaks Hacked Customer Server (Tech Times, 2026-09-12)
  3. Gorilla and Yotta Expand India AI Infra in $2.8B Deal (Yotta, 2026-04-30)
  4. Yotta to Commence Construction of Two More Data Center Buildings in its Greater Noida DC Park (Yotta, 2021-11-29)
  5. Yotta to construct 2 more Data Centres in January 2022 (W.Media, 2021-11-29)
  6. Yotta Data Center, Noida: North India's first major Digital Hub (Biltrax Media, 2024-11-09)
  7. Agenda of 761st meeting of State Level Environment Impact Assessment Authority, Uttar Pradesh (SEIAA Uttar Pradesh / environmentclearance.nic.in, 2023-09-30)
  8. Yotta to Deploy One of Asia's Largest NVIDIA Blackwell HGX B300 Superclusters with Over 20,000 NVIDIA Blackwell Ultra GPUs; NVIDIA to establish one of APAC's largest DGX Cloud Cluster in India (Yotta Data Services, 2026-02-18)
  9. Nidar Infrastructure Limited Form 424B3 proxy statement/prospectus (Nidar Infrastructure Ltd (SEC EDGAR), 2025-11-06)
  10. Yotta's 85,000 GPU bet is bigger than the IndiaAI Mission (Analytics India Magazine, 2026-07-06)

Same campus, Yotta Greater Noida Data Center Park

More in NCR

Also run by Yotta

Definitions and sourcing rules · CC BY-NC 4.0 · corrections@arusgrid.com