ArusGrid tracks 3 active data center projects operated by Yotta, with 141 MW of planned IT load, across India. Of these, 2 are operational and 1 is under construction. Projects under construction or commissioning account for 60 MW.

ArusGrid classes the operator as colocation. Projects appear under the names Yotta Data Services. The largest project is Yotta D2 at 60 MW in NCR, under construction. AI workloads are confirmed at 2 sites. Named funders across its projects are Hiranandani Group. Disclosed tenants across its projects are Nvidia DGX Cloud and IndiaAI Mission.

Open the mapRelationship graph

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
Yotta D2Greater NoidaUnder construction60undisclosedYotta Data ServicesConfirmed
Yotta NM1PanvelOperational52undisclosedYotta Data ServicesConfirmed
Yotta D1Greater NoidaOperational29undisclosedYotta Data ServicesLikely

Markets where it builds

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.