ArusGridProject
Directory › United Arab Emirates › Abu Dhabi › Gulf Data Hub Abu Dhabi (ICAD)

Gulf Data Hub Abu Dhabi (ICAD)

Abu Dhabi, United Arab Emirates · Abu Dhabi market · location approximate to district level

Gulf Data Hub Abu Dhabi (ICAD) is a data center project in Abu Dhabi, United Arab Emirates, operated by Gulf Data Hub. It is operational and expanding. It is planned for 64 MW of IT load. The operator reports 16 MW running.

Latest change on record: moved to expanding on 28 August 2026.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
64 MW
Running now
16 MW
Operator
Gulf Data Hub
Colocation
AI workloads
No signal either way
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How United Arab Emirates approves, powers and taxes data centers is on Data center rules in United Arab Emirates.

How well evidenced is it

Running capacity. The site is operational or expanding. On record: named funder, dated, sized phase, dated source in the last 24 months. Criteria.

AI workloads

StatusNo signal either way

Multi-tenant colocation with no AI tenant, workload or cooling disclosure.

Access to AI chips

GradeNo public signal

Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria.

Country Group A:5 with Supplement No. 8 approved end users · Country Group A:5 with Supplement No. 8 approved end users (2026-07-14) source

Phases

ICAD 1 · Operational16 MW, target 2022

Stage history

2021-07Under construction · midisgroup.com
2026-08-28Expanding · gulfdatahub.ae

Who is behind it

OperatorGulf Data Hub · Colocation
Funder, EquityKKR

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Project team
Mechanical and electrical worksSite & Power DK · Nov 2022 · completed Confirmed source ↗
ICAD III data center MEP works, engineering, supply, installation, five levels of testing and commissioning, Tier III TCDD and TCCF
Land
Industrial estateIndustrial City of Abu Dhabi (ICAD), Mussafah · 32,000 sqm · Nov 2022 Reported source ↗
Plot for ICAD III, 6,500 sqm initial white space in up to 18,000 sqm built-up area

Sources

  1. Gulf Data Hub locations (Gulf Data Hub, 2026-08-28)
  2. Site & Power DK announce successful completion of Gulf Data Hub ICAD III in Abu Dhabi (Midis Group, 2022-11-30)

More in Abu Dhabi

Also run by Gulf Data Hub

Definitions and sourcing rules · CC BY-NC 4.0 · corrections@arusgrid.com