Oman was researched on 27 September 2026 and no data centre at or above 20MW IT load, and none with a confirmed hyperscaler or AI tenant, was found. Equinix MC1 and SN1 and Ooredoo's Salalah site are interconnection colo below the bar; Datamount Al Bandar publishes racks, not megawatts; Oman Data Park deployed Nvidia H200 GPUs with no site or capacity stated; Royal Decree 50/2026 created an AI Special Zone with no anchor project. Oman stays in scope and is rechecked at each Gulf refresh.
The US export control position for advanced AI chips in Oman, as of 27 September 2026, is recorded as “Licence required as enforced (Country Group D:4), no named authorisation found”.