ArusGrid tracks 5 active data center projects in Noida, India, with 189 MW of planned IT load. Of these, 2 are operational, 1 is operational and expanding and 2 are announced only. Operators have disclosed 32 MW actually running.
Noida sits in the NCR market, which is the level at which brokers publish vacancy and ArusGrid compares supply. The largest project is AdaniConneX Noida at 60 MW, operational and expanding. The operators with the most planned capacity here are AdaniConneX (60 MW across 1 project), NTT (53 MW across 1 project) and STT GDC (50 MW across 2 projects).
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| AdaniConneX Noida | Noida | Expanding | 60 * | 10 | AdaniConneX | Likely |
| NTT Noida 2 campus | Noida | Operational | 53 | 22 | NTT Global Data Centers | Confirmed |
| STT Noida 3 | Noida | Announced | 28 | undisclosed | STT GDC India | No signal either way |
| Sify Noida 02 | Noida | Operational | 26 | undisclosed | Sify Infinit Spaces | Likely |
| STT Noida 2 | Noida | Announced | 22 | undisclosed | STT GDC India | No signal either way |
AdaniConneX · NTT · STT GDC · Sify
All projects in India · Full directory