Korat (Nakhon Ratchasima), Nakhon Ratchasima, Thailand · Other Thailand market · location approximate to city level
Gorilla Technology Korat AI Campus is a data center project in Korat (Nakhon Ratchasima), Thailand, operated by Gorilla Technology Group. It is at the land and permitting stage. It is planned for 150 MW of IT load.
Latest change on record: entered the record as land and permitting on 5 May 2026.
Will it get built?Open question2 of 7 gates passed
✓ Land secured○ Power arranged○ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed○ Construction started
Next gate to watch: Power arranged.
Your call. Will it be built?
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.
How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. On record: named funder, three or more sources, dated source in the last 24 months. Criteria.
AI workloads
StatusLikely
Explicit AI campus: six data halls, illustrative all-GB300 config at ~142kW/rack and 72 GPUs/rack supporting ~76,000 GPUs at full deployment. Density is a stated plan, not a deployed system - hence 'likely' not 'confirmed'.
Access to AI chips
GradeNo US licence required
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria.
Phases
Phase 1 · Land and permittingSize not published, target 2027
OperatorGorilla Technology Group · Local developer
Funder, EquityGorilla Technology Group
Who uses the compute
Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.