ArusGridProject
Directory › Thailand › DC POWER BN1, Bangna

DC POWER BN1, Bangna

Bangna-Trat km 4.5, Bangkok, Thailand · Bangkok metro market · location approximate to district level

DC POWER BN1, Bangna is a data center project in Bangna-Trat km 4.5, Thailand, operated by DC POWER BN1 Co., Ltd. It is under construction. It is planned for 24 MW of IT load.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
24 MW
Running now
Not disclosed
Operators rarely publish this
Operator
DC POWER BN1 Co., Ltd.
Joint venture
AI workloads
No signal either way
Evidence grade
Corroborated
Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesNo
Dated source in the last 24 monthsNo

AI workloads

StatusNo signal either way

No public signal either way.

Phases

Buildings A-D (4 x 6MW) · Under construction24 MW, target 2025

Who is behind it

OperatorDC POWER BN1 Co., Ltd. · Joint venture
Funder, Joint venture partnerSTECON Power (STECON Group)
Funder, Joint venture partnerSITEM Corporation
Funder, Joint venture partnerMyTelehaus

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Announced investment, 2023-10THB 8bn (about US$219m)
Who builds it
Design and build contractorSino-Thai Engineering and Construction PCL (STECON) · Oct 2023 Reported source ↗
Engineering and construction of four DC buildings, phases C and D first

Sources checked 2026-07-13

  1. mitihoon.com
  2. w.media

More in Bangkok metro

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. Dataset updated 2026-09-26.