ArusGridOperator
Directory › Operators › Humain

Humain data center projects

Saudi Arabia · dataset updated 2026-09-27

ArusGrid tracks 4 active data center projects operated by Humain, with 250 MW of planned IT load, across Saudi Arabia. Of these, 2 are under construction, 1 is at the land and permitting stage and 1 is announced only. Projects under construction or commissioning account for 200 MW.

ArusGrid classes the operator as colocation. The largest project is Humain Dammam campus at 100 MW in Dammam / Eastern Province, under construction. Named funders across its projects are Public Investment Fund. Disclosed tenants across its projects are xAI.

Open the mapRelationship graph

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
Humain Dammam campusDammamUnder construction100undisclosedHumainLikely
Humain Riyadh campusRiyadhUnder construction100undisclosedHumainLikely
Humain / xAI Riyadh campusRiyadhAnnounced50undisclosedHumainLikely
Humain Al-Saad campusRiyadhLand and permittingnone publishedundisclosedHumainLikely

Markets where it builds

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.