ArusGridMarket
Directory › Bahrain › Manama

Data center projects in Manama

Bahrain · The Gulf · dataset updated 2026-09-27

ArusGrid tracks 2 active data center projects in Manama, Bahrain, with 60 MW of planned IT load. Of these, 1 is under construction and 1 is on hold. Projects under construction or commissioning account for 60 MW.

The largest project is center3 Bahrain Data Center Park at 60 MW, under construction. The operators with the most planned capacity here are center3 (60 MW across 1 project) and AWS (1 project). No third party publishes a colocation vacancy rate for Manama, and ArusGrid does not estimate one.

Grid power for a large industrial user in Bahrain costs about US$0.095 per kWh as of September 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Bahrain, as of 27 September 2026, is recorded as “Licence required as enforced (Country Group D:4), no named authorisation found”.

Open the mapPipeline view

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
center3 Bahrain Data Center ParkAl QurainUnder construction60undisclosedcenter3 (stc Group)Likely
AWS Middle East (Bahrain) region, me-south-1ManamaOn holdnone publishedundisclosedAmazon Web ServicesNo signal either way

Operators here with their own page

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.