ArusGrid tracks 2 active data center projects in Manama, Bahrain, with 60 MW of planned IT load. Of these, 1 is under construction and 1 is on hold. Projects under construction or commissioning account for 60 MW.
The largest project is center3 Bahrain Data Center Park at 60 MW, under construction. The operators with the most planned capacity here are center3 (60 MW across 1 project) and AWS (1 project). No third party publishes a colocation vacancy rate for Manama, and ArusGrid does not estimate one.
Grid power for a large industrial user in Bahrain costs about US$0.095 per kWh as of September 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Bahrain, as of 27 September 2026, is recorded as “Licence required as enforced (Country Group D:4), no named authorisation found”.
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| center3 Bahrain Data Center Park | Al Qurain | Under construction | 60 | undisclosed | center3 (stc Group) | Likely |
| AWS Middle East (Bahrain) region, me-south-1 | Manama | On hold | none published | undisclosed | Amazon Web Services | No signal either way |
All projects in Bahrain · Full directory