ArusGrid tracks 5 active data center projects in Karawang, Indonesia, with 748 MW of planned IT load. Of these, 2 are operational, 2 are operational and expanding and 1 is under construction. Projects under construction or commissioning account for 100 MW. Operators have disclosed 27 MW actually running.
Karawang sits in the Greater Jakarta market, which is the level at which brokers publish vacancy and ArusGrid compares supply. The largest project is DCI H2 Campus (H2-01, H2-02), Karawang at 600 MW, operational and expanding. The operators with the most planned capacity here are DCI Indonesia (600 MW across 1 project), BDx (100 MW across 1 project) and Microsoft (48 MW across 1 project).
| Project | City | Stage | Planned MW | Running MW | Operator | AI |
|---|---|---|---|---|---|---|
| DCI H2 Campus (H2-01, H2-02), Karawang | Karawang | Expanding | 600 | 27 | DCI Indonesia | Likely |
| BDx CGK5, Suryacipta City of Industry | Karawang | Under construction | 100 | undisclosed | BDx Indonesia | Likely |
| Microsoft JKT09 / JKT02 (KIIC Karawang campus) | Karawang (Karawang International Industrial City) | Expanding | 48 * | undisclosed | Microsoft | Confirmed |
| AWS CGK Kutanegara (Karawang) | Karawang | Operational | none published | undisclosed | Amazon Web Services | Likely |
| AWS CGK Margamulya (KIIC Karawang) | Karawang | Operational | none published | undisclosed | Amazon Web Services | Likely |
DCI Indonesia · BDx · Microsoft · AWS