How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusLikely
Hyperscaler AI hub announced 2025 at gigawatt scale; no dated GPU or cooling disclosure yet.
Access to AI chips
GradeNo US licence required
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectYes
Named chip-vendor partnershipNo
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Phases
Adivivaram campus (120 acres) · Land and permittingSize not published
Tarluvada campus (200 acres) · Under constructionSize not published
Rambilli / Achyutapuram campus (160 acres) · Land and permittingSize not published
Stage history
Who is behind it
OperatorAdaniConneX · Joint venture
Funder, EquityGoogle
Funder, Joint venture partnerAdani Enterprises
Funder, Joint venture partnerEdgeConneX
Client, confirmedGoogle
Money at this site
Announced investment, 2025-10US$15bn
The figure covers several facilities.
Land
Allocated byGovernment of Andhra Pradesh (APIIC) · 160 acres · INR 26.46m (≈US$3m) · leased · Feb 2026 Reported source ↗ Adivivaram and Mudasarlova villages; annual rent Rs 26.45 crore with 5% escalation every five years; 11-year initial term extendable to 30; allotted without auction to Vizag Hyperscale Data Centre Park Ltd (Adani Infra); allotment orders February 2026, advance possession April 2026; PIL pending in AP High Court (Sept 2026) over environmental clearance and temple land
Allocated byGovernment of Andhra Pradesh · 480 acres · Oct 2025 Reported source ↗ Three linked campuses: Adivivaram 120, Tarluvada 200, Rambilli-Achyutapuram 160 acres, as reported at announcement