Data center rules in Thailand

Checked against sources 2026-10-03 · 32 rules and proposals, each with a dated source

Thailand has frozen its data centre pipeline while it rewrites the rules. On 4 September 2026 a new Cabinet-level board paused construction on 49 projects and froze approvals for 117 more. New standards on building definition, zoning, power tariffs, water and fuel storage are being finalised in October 2026. Until those standards are approved and published, no new project should expect permits, utility connections or BOI approval.

Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”.

Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

Approvals and licensing 8

National Data Center Business Policy Committee createdIn force

The Cabinet approved a Prime Minister's Office regulation on 5 August 2026 setting up a national committee to oversee data centre investment. Deputy Prime Minister and Finance Minister Ekniti Nitithanprapas chairs it. It is the first body with authority over data centres across all ministries.

Effective August 2026 · Cabinet / Office of the Prime Minister
49 projects paused and 117 approvals frozenPaused

At its first meeting on 4 September 2026 the committee paused construction on 49 data centres and froze approval of 117 more, which is 166 projects in total. It gave four subcommittees one month to write minimum standards. They cover economic benefit, infrastructure, sites and buildings, and environment. The pause followed an unlicensed diesel storage and leak incident at a Rama 9 data centre in Bangkok.

Since 2026-09-04 · National Data Center Business Policy Committee
Data centres get their own building categoryProposed

On 1 October 2026 the committee approved a separate legal definition for data centre buildings. Until now they were classed as large buildings, and some were permitted as warehouses or offices. Five size classes based on power use will set rules on safety, structure, water reserves and backup fuel tanks. The Department of Public Works and Town and Country Planning is finalising the technical rules, and the changes go to Cabinet within about a month.

National Data Center Business Policy Committee / Ministry of Interior
BOI four-pillar screening and energy subcommitteeIn force

BOI now screens data centre projects on four pillars. These are benefit to Thailand, energy security, water, and environment and zoning. Since July 2026 applicants need approval from a new subcommittee on energy management and data centre screening. This also applies to promoted projects that add more than 30% IT load. This replaced the ERC grid-capacity letter that had been required for new applications from 30 March 2026.

Effective July 2026 · Board of Investment (BOI)
Draft digital infrastructure law with licensingProposed

A draft bill would require data centre operators to hold a licence from the Minister of Digital Economy and Society and to be Thai-registered companies. It would require an environmental impact assessment (EIA), siting in factory-zoned areas, and own water and power sources for large sites. Unlicensed operation could bring up to 5 years in prison. The public hearing runs 3 September 2026 to 15 October 2026, and the size thresholds are left to later regulations.

Ministry of Digital Economy and Society (DES)
50% Thai content rule for licensed operatorsProposed

Proposed conditions would require at least 50% of structural materials, construction work and electrical systems to come from Thai makers where supply, standards and price allow. They would apply to data centre operators seeking telecom licences, and existing operators would get 90 days to comply. NESDC said the rules should be in force by mid-October 2026.

NBTC / National Data Center Business Policy Committee
Bangkok inspections and permit freezeIn force

The Bangkok Metropolitan Administration (BMA) counted 49 data centres in the city, most under 2MW and inside office buildings. It runs random checks on building standards, fuel, water, heat, noise and fire safety. It has suspended new data centre permit applications until national guidelines are issued. The Interior Ministry told utilities to hold water and power connections for unapproved new projects.

Effective September 2026 · Bangkok Metropolitan Administration / Ministry of Interior
Diesel storage above 15,000 litres needs a permitIn force

Under the Fuel Control Act 1999, storing more than 15,000 litres of fuel needs a permit. The Rama 9 facility allegedly held about 200,000 litres without one, and a criminal complaint was filed. Penalties are up to two years in prison or a fine up to 200,000 THB.

Department of Energy Business

Power 7

Data centres become a separate tariff classProposed

On 15 July 2026 the National Energy Policy Council (NEPC) meeting 2/2569 approved a separate electricity tariff class for data centres, called category 9. The rate is meant to be higher than other groups so households do not carry the cost. The Energy Regulatory Commission (ERC) has not yet set the rate. Press reports have floated 5 to 6 THB per kWh, and this figure is unconfirmed.

NEPC / ERC
Two data centre rates by power sourceProposed

On 1 October 2026 the data centre committee agreed a two-rate design. Sites using clean energy or Direct PPAs would pay less than sites drawing gas-fired grid power. A subcommittee meets on 6 October 2026 to set the rate details.

National Data Center Business Policy Committee / Ministry of Energy
Ft charge for September to December 2026In force

Ft is the automatic fuel adjustment charge added to every unit of power. ERC set Ft at 16.23 satang per unit for September to December 2026. The average tariff fell to about 3.89 THB per unit. Data centres pay industrial rates above 3 THB per unit until their own class takes effect.

Effective September 2026 · Energy Regulatory Commission (ERC)
Direct PPA 2,000MW cap scrappedEnded

A Direct PPA lets a user buy renewable power straight from a generator over the state grid, which is called third-party access. The pilot began with 2,000MW reserved for data centres. In August 2026 NEPC removed the cap and opened direct clean power purchases to all industries.

Ended August 2026 · NEPC / Ministry of Energy
Grid-use security deposit of 4.5m THB per MWProposed

ERC plans a deposit of 4.5 million THB per MW to stop speculative capacity bookings. Half would be returned when a site uses 50% of planned power within a year, and all of it at 70%. The measure was awaiting Cabinet approval and is not yet confirmed as in force.

Energy Regulatory Commission (ERC)
60% clean power minimum and new ERC licenceProposed

The Energy Ministry set four power criteria for data centres. They include a clean energy share of at least 60% in line with the new power plan, plus safety rules for backup batteries and diesel generators. Separately, ERC proposed a licence for selling power to data centres, with its hearing open 19 September 2026 to 18 October 2026.

Ministry of Energy / ERC
Utility Green Tariff programmeIn force

The Utility Green Tariff (UGT) lets large users buy certified renewable power from the state utilities. UGT1 launched in January 2025 with a premium of 0.0594 THB per unit. UGT2 adds a choice of specific solar or wind sources.

Effective January 2025 · ERC / EGAT / MEA / PEA

Incentives 3

BOI tax holidays of 5 or 8 yearsIn force

Since 1 July 2025 BOI grants an 8-year corporate income tax exemption to high-efficiency data centres and 5 years to others. Both are capped at 100% of investment. High efficiency is judged on PUE (power usage effectiveness), water efficiency and benefits to Thailand such as training and local supply chains.

Effective 2025-07-01 · Board of Investment (BOI)
Incentive review ordered in August 2026Status unclear

The Deputy Prime Minister told BOI to review data centre incentives. The review weighs water, power, environment and real benefit to Thai citizens. He also said large operators should build their own power plants. No revised incentive package has been published.

Board of Investment (BOI)
BOI pipeline of 42 promoted projectsPaused

BOI has promoted 42 data centre projects from 2024 to 2026 with 3,400MW of IT load and about 750 billion THB of investment. Press reports say BOI has made no new data centre approvals since April 2026 while the rules are rewritten.

Board of Investment (BOI)

Data rules 5

PDPA cross-border transfer rulesIn force

Two notifications under sections 28 and 29 of the Personal Data Protection Act took effect on 24 March 2024. Personal data may leave Thailand to destinations with adequate protection or under safeguards such as binding corporate rules, standard contract clauses or certification. They impose no general data localisation rule.

Effective 2024-03-24 · Personal Data Protection Committee (PDPC)
Proposed localisation of Thai personal dataProposed

The draft digital infrastructure bill would require personal data of Thai people and Thai corporate data to stay in Thailand by default. Exceptions would be set in ministerial regulations. The hearing closes 15 October 2026.

Ministry of Digital Economy and Society (DES)
Go Cloud First and government data classesStatus unclear

Under the Cabinet's Go Cloud First policy, government agencies must prefer cloud for new IT projects. Draft guidelines from the Digital Government Development Agency (DGA) sort government data into three classes. The most sensitive class must stay in sovereign or state-controlled clouds in Thailand. The guidelines were in draft at the August 2025 hearing, and their final status is unconfirmed.

Digital Government Development Agency (DGA)
NCSA cloud security standard in forceIn force

The National Cyber Security Agency (NCSA) cloud security standard took effect on 10 September 2026. It covers government agencies, critical information infrastructure (CII) operators and the cloud providers that serve them. Systems must be classed by impact level and certified against minimum controls.

Effective 2026-09-10 · National Cyber Security Agency (NCSA)
Cybersecurity Act amendment on CII suppliersProposed

A draft amendment to the Cybersecurity Act would make CII operators police their outside service providers. Providers would get a 60-day window to fix problems, and non-compliant providers would be listed. Cloud and data centre suppliers to CII would face these duties through their contracts.

National Cyber Security Committee / NCSA

Water and cooling 4

Water plans required from operatorsProposed

ERC's proposed screening framework requires data centre operators to submit water management plans. BOI also screens water source, cooling technology, recycling and drought planning.

ERC / Board of Investment (BOI)
Large sites to use their own waterProposed

The draft digital infrastructure bill would require data centres above a set size to secure their own water sources. They could not draw on public supply. The size threshold is not yet defined.

Ministry of Digital Economy and Society (DES)
EEC water demand estimateIn force

The Royal Irrigation Department estimates the 16 BOI-approved data centres in the Eastern Economic Corridor (EEC) will need 42.4 to 50 million cubic metres of water a year. It is planning supply with the Office of the National Water Resources.

Royal Irrigation Department
Community opposition in Ban Chang, RayongStatus unclear

Residents in Ban Chang, Rayong, in the EEC have opposed data centre projects over water and power use. One developer responded with public forums and a joint monitoring model. Its water supply is about 35% municipal and 65% private sources.

Local communities / EEC

On the clock 5

Data centre tariff rate decisionProposed

A subcommittee meets on 6 October 2026 to set details of the two data centre electricity rates. ERC must then set and announce the category 9 rate.

Expected 2026-10-06 · Ministry of Energy / ERC
Minimum standards due mid-OctoberProposed

NESDC said the new data centre rules should be final by mid-October 2026. Under the draft, sites of 100MW or more would count as hyperscale and industrial-type sites would go in industrial estates. The one-month deadline from 4 September 2026 has passed without published standards. On 1 October 2026 officials said subcommittee criteria would be done within about a week.

Expected October 2026 · NESDC / National Data Center Business Policy Committee
Cabinet vote on building definitionProposed

The new data centre building category and the five size classes go to Cabinet within about a month of 1 October 2026. A transition period for existing operators is promised, and its length is not yet set.

Expected November 2026 · Cabinet / Ministry of Interior
Public hearings closing in OctoberProposed

The hearing on the draft digital infrastructure bill closes on 15 October 2026. The hearing on ERC's data centre power licence closes on 18 October 2026.

Expected 2026-10-15 · DES / ERC
ERC data centre power rules by year endProposed

ERC plans to finish its full set of rules on selling power to data centres by the end of 2026. These cover grid supply, green power, Direct PPA and possible on-site generation, and ERC will present them to the data centre committee.

Expected December 2026 · Energy Regulatory Commission (ERC)

Searched and not confirmed

What this research looked for and could not confirm from a primary or credible source. Listed so the gaps are visible.

Rules in other countries

Each rule is stated as its source states it, with the issuing body and the date it took effect or is expected. Statuses are In force, Proposed (a draft, consultation or announced plan with no legal effect yet), Paused, Ended and Status unclear. Rules change, so check the date beside each item and the source before relying on it. This page is not legal advice. Corrections go to [email protected]. Data is CC BY-NC 4.0.