ArusGrid tracks 2 active data center projects operated by Digital Edge in Indonesia, with 523 MW of planned IT load. Of these, 1 is operational and 1 is under construction. Projects under construction or commissioning account for 500 MW.

Its Indonesia projects sit in Greater Jakarta. The largest is Digital Edge CGK Campus (CGK1 to CGK4), Cikarang at 500 MW, under construction. Outside Indonesia, Digital Edge has 4 active projects on record in India, Malaysia and Thailand.

Open the mapPipeline view

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
Digital Edge CGK Campus (CGK1 to CGK4), CikarangCikarang, BekasiUnder construction500undisclosedDigital EdgeConfirmed
Digital Edge EDGE2, JakartaJakartaOperational23undisclosedDigital EdgeNo signal either way

Markets

Digital Edge in other countries

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to [email protected]. This page is generated from the dataset, so it cannot drift from the map.