<title>ArusGrid, what moved</title>
<link>https://arusgrid.com/news</link>
<description>Dated stage moves on the data center buildout across Southeast Asia, the Gulf, India and China, project by project.</description>
<atom:link href="https://arusgrid.com/feed.xml" rel="self" type="application/rss+xml"/>
<item><title>AM AI Factory Vizag moved to land and permitting</title><link>https://arusgrid.com/project/in-vtz-amai-vizag</link><guid isPermaLink="false">in-vtz-amai-vizag:2026-11-10:land_permitting</guid><pubDate>Tue, 10 Nov 2026 00:00:00 +0000</pubDate><description>AM AI Factory Vizag, Bheemunipatnam, India. 512 MW planned IT load. Moved to land and permitting on 10 November 2026.</description></item>
<item><title>Equinix SG6 moved to operational</title><link>https://arusgrid.com/project/sg-sg-equinix-sg6</link><guid isPermaLink="false">sg-sg-equinix-sg6:2026-11-06:operational</guid><pubDate>Fri, 06 Nov 2026 00:00:00 +0000</pubDate><description>Equinix SG6, Singapore, Singapore. 20 MW planned IT load. Moved to operational on 6 November 2026.</description></item>
<item><title>Google (Pearl Computing) Elmina Data Centre &amp; Cloud Region entered the record as expanding</title><link>https://arusgrid.com/project/my-sel-google-elmina</link><guid isPermaLink="false">my-sel-google-elmina:2026-11-04:expanding</guid><pubDate>Wed, 04 Nov 2026 00:00:00 +0000</pubDate><description>Google (Pearl Computing) Elmina Data Centre &amp; Cloud Region, City of Elmina, Shah Alam, Malaysia. Entered the record as expanding on 4 November 2026.</description></item>
<item><title>STT Noida 2 moved to operational</title><link>https://arusgrid.com/project/in-ncr-stt-noida2</link><guid isPermaLink="false">in-ncr-stt-noida2:2026-11-03:operational</guid><pubDate>Tue, 03 Nov 2026 00:00:00 +0000</pubDate><description>STT Noida 2, Noida, India. 22 MW planned IT load. Moved to operational on 3 November 2026.</description></item>
<item><title>SMX01 (SM+ / LG Sinar Mas), Jakarta CBD moved to operational</title><link>https://arusgrid.com/project/id-jakarta-sinarmas-smx01</link><guid isPermaLink="false">id-jakarta-sinarmas-smx01:2026-11-02:operational</guid><pubDate>Mon, 02 Nov 2026 00:00:00 +0000</pubDate><description>SMX01 (SM+ / LG Sinar Mas), Jakarta CBD, Jakarta, Indonesia. 27 MW planned IT load. Moved to operational on 2 November 2026.</description></item>
<item><title>Vyoma.AI Chennai 52MW AI-ready data centre entered the record as under construction</title><link>https://arusgrid.com/project/in-maa-ltvyoma-aifactory52</link><guid isPermaLink="false">in-maa-ltvyoma-aifactory52:2026-10-28:under_construction</guid><pubDate>Wed, 28 Oct 2026 00:00:00 +0000</pubDate><description>Vyoma.AI Chennai 52MW AI-ready data centre, Sriperumbudur, India. 52 MW planned IT load. Entered the record as under construction on 28 October 2026.</description></item>
<item><title>AdaniConneX Ghansoli campus entered the record as under construction</title><link>https://arusgrid.com/project/in-mum-adaniconnex-ghansoli</link><guid isPermaLink="false">in-mum-adaniconnex-ghansoli:2026-10-28:under_construction</guid><pubDate>Wed, 28 Oct 2026 00:00:00 +0000</pubDate><description>AdaniConneX Ghansoli campus, Ghansoli, Navi Mumbai, India. 220 MW planned IT load. Entered the record as under construction on 28 October 2026.</description></item>
<item><title>Colt Airoli expansion campus moved to under construction</title><link>https://arusgrid.com/project/in-mum-colt-airoli-expansion</link><guid isPermaLink="false">in-mum-colt-airoli-expansion:2026-10-15:under_construction</guid><pubDate>Thu, 15 Oct 2026 00:00:00 +0000</pubDate><description>Colt Airoli expansion campus, Navi Mumbai (Airoli), India. 100 MW planned IT load. Moved to under construction on 15 October 2026.</description></item>
<item><title>CtrlS Bodh Gaya AI Factory entered the record as announced</title><link>https://arusgrid.com/project/in-oth-ctrls-bodhgaya</link><guid isPermaLink="false">in-oth-ctrls-bodhgaya:2026-10-13:announced</guid><pubDate>Tue, 13 Oct 2026 00:00:00 +0000</pubDate><description>CtrlS Bodh Gaya AI Factory, Bodh Gaya, India. 150 MW planned IT load. Entered the record as announced on 13 October 2026.</description></item>
<item><title>ReNew Green Data Centre Park, MMR entered the record as announced</title><link>https://arusgrid.com/project/in-mum-renew-mmr</link><guid isPermaLink="false">in-mum-renew-mmr:2026-10-09:announced</guid><pubDate>Fri, 09 Oct 2026 00:00:00 +0000</pubDate><description>ReNew Green Data Centre Park, MMR, Navi Mumbai and Raigad (Panvel, Khalapur, Taloja, Bhokharpada), India. Entered the record as announced on 9 October 2026.</description></item>
<item><title>AdaniConneX Taloja campus entered the record as announced</title><link>https://arusgrid.com/project/in-mum-adaniconnex-taloja</link><guid isPermaLink="false">in-mum-adaniconnex-taloja:2026-10-06:announced</guid><pubDate>Tue, 06 Oct 2026 00:00:00 +0000</pubDate><description>AdaniConneX Taloja campus, Taloja, Navi Mumbai, India. 240 MW planned IT load. Entered the record as announced on 6 October 2026.</description></item>
<item><title>Humain and center3 Riyadh AI data centre entered the record as announced</title><link>https://arusgrid.com/project/sa-ruh-humain-center3</link><guid isPermaLink="false">sa-ruh-humain-center3:2026-10-06:announced</guid><pubDate>Tue, 06 Oct 2026 00:00:00 +0000</pubDate><description>Humain and center3 Riyadh AI data centre, Riyadh, Saudi Arabia. 50 MW planned IT load. Entered the record as announced on 6 October 2026.</description></item>
<item><title>BDx CGK4 AI Campus, Jatiluhur moved to on hold</title><link>https://arusgrid.com/project/id-purwakarta-bdx-cgk4</link><guid isPermaLink="false">id-purwakarta-bdx-cgk4:2026-09-30:on_hold</guid><pubDate>Wed, 30 Sep 2026 00:00:00 +0000</pubDate><description>BDx CGK4 AI Campus, Jatiluhur, Jatiluhur, Purwakarta, Indonesia. 120 MW planned IT load. Moved to on hold on 30 September 2026.</description></item>
<item><title>AWS Sepang (Dengkil) land entered the record as announced</title><link>https://arusgrid.com/project/my-sel-aws-sepang</link><guid isPermaLink="false">my-sel-aws-sepang:2026-09-28:announced</guid><pubDate>Mon, 28 Sep 2026 00:00:00 +0000</pubDate><description>AWS Sepang (Dengkil) land, Sepang (Dengkil), Malaysia. Entered the record as announced on 28 September 2026.</description></item>
<item><title>Sify Rabale campus moved to expanding</title><link>https://arusgrid.com/project/in-mum-sify-rabale</link><guid isPermaLink="false">in-mum-sify-rabale:2026-09-27:expanding</guid><pubDate>Sun, 27 Sep 2026 00:00:00 +0000</pubDate><description>Sify Rabale campus, Navi Mumbai, India. 136 MW planned IT load. Moved to expanding on 27 September 2026.</description></item>
<item><title>Sify Noida 02 moved to operational</title><link>https://arusgrid.com/project/in-ncr-sify-noida02</link><guid isPermaLink="false">in-ncr-sify-noida02:2026-09-27:operational</guid><pubDate>Sun, 27 Sep 2026 00:00:00 +0000</pubDate><description>Sify Noida 02, Noida, India. 26 MW planned IT load. Moved to operational on 27 September 2026.</description></item>
<item><title>CapitaLand DC ITPB Bengaluru entered the record as announced</title><link>https://arusgrid.com/project/in-blr-capitaland-itpb</link><guid isPermaLink="false">in-blr-capitaland-itpb:2026-09-25:announced</guid><pubDate>Fri, 25 Sep 2026 00:00:00 +0000</pubDate><description>CapitaLand DC ITPB Bengaluru, Whitefield, Bengaluru, India. 27 MW planned IT load. Entered the record as announced on 25 September 2026.</description></item>
<item><title>STT GDC Bengaluru Devanahalli campus entered the record as announced</title><link>https://arusgrid.com/project/in-blr-sttgdc-devanahalli</link><guid isPermaLink="false">in-blr-sttgdc-devanahalli:2026-09-25:announced</guid><pubDate>Fri, 25 Sep 2026 00:00:00 +0000</pubDate><description>STT GDC Bengaluru Devanahalli campus, Devanahalli, India. 100 MW planned IT load. Entered the record as announced on 25 September 2026.</description></item>
<item><title>Adani High Density Data Centre Park, Naraj entered the record as announced</title><link>https://arusgrid.com/project/in-ctk-adani-naraj</link><guid isPermaLink="false">in-ctk-adani-naraj:2026-09-25:announced</guid><pubDate>Fri, 25 Sep 2026 00:00:00 +0000</pubDate><description>Adani High Density Data Centre Park, Naraj, Cuttack (Naraj), India. Entered the record as announced on 25 September 2026.</description></item>
<item><title>Galaxy Data Center (Silicon Tech Park, Rayong) entered the record as under construction</title><link>https://arusgrid.com/project/th-ryg-galaxy-stp</link><guid isPermaLink="false">th-ryg-galaxy-stp:2026-09-25:under_construction</guid><pubDate>Fri, 25 Sep 2026 00:00:00 +0000</pubDate><description>Galaxy Data Center (Silicon Tech Park, Rayong), Ban Chang, Thailand. 310 MW planned IT load. Entered the record as under construction on 25 September 2026.</description></item>
<item><title>SentraForge AI Puri campus entered the record as announced</title><link>https://arusgrid.com/project/in-pur-sentraforge-puri</link><guid isPermaLink="false">in-pur-sentraforge-puri:2026-09-24:announced</guid><pubDate>Thu, 24 Sep 2026 00:00:00 +0000</pubDate><description>SentraForge AI Puri campus, Puri, India. 120 MW planned IT load. Entered the record as announced on 24 September 2026.</description></item>
<item><title>BDx CGK4 AI Campus, Jatiluhur entered the record as under construction</title><link>https://arusgrid.com/project/id-purwakarta-bdx-cgk4</link><guid isPermaLink="false">id-purwakarta-bdx-cgk4:2026-09-22:under_construction</guid><pubDate>Tue, 22 Sep 2026 00:00:00 +0000</pubDate><description>BDx CGK4 AI Campus, Jatiluhur, Jatiluhur, Purwakarta, Indonesia. 120 MW planned IT load. Entered the record as under construction on 22 September 2026.</description></item>
<item><title>Tera Data Centers Port Dickson (Eco Business Park 7) entered the record as announced</title><link>https://arusgrid.com/project/my-ns-tera-portdickson</link><guid isPermaLink="false">my-ns-tera-portdickson:2026-09-22:announced</guid><pubDate>Tue, 22 Sep 2026 00:00:00 +0000</pubDate><description>Tera Data Centers Port Dickson (Eco Business Park 7), Port Dickson (Mukim Jimah), Malaysia. Entered the record as announced on 22 September 2026.</description></item>
<item><title>DayOne Nongsa Digital Park Campus (NDP1-3) moved to operational</title><link>https://arusgrid.com/project/id-riau-dayone-ndp</link><guid isPermaLink="false">id-riau-dayone-ndp:2026-09-20:operational</guid><pubDate>Sun, 20 Sep 2026 00:00:00 +0000</pubDate><description>DayOne Nongsa Digital Park Campus (NDP1-3), Batam, Indonesia. 72 MW planned IT load. Moved to operational on 20 September 2026.</description></item>
<item><title>AWS Middle East (Bahrain) region, me-south-1 moved to on hold</title><link>https://arusgrid.com/project/bh-man-aws-me-south-1</link><guid isPermaLink="false">bh-man-aws-me-south-1:2026-09-16:on_hold</guid><pubDate>Wed, 16 Sep 2026 00:00:00 +0000</pubDate><description>AWS Middle East (Bahrain) region, me-south-1, Manama, Bahrain. Moved to on hold on 16 September 2026.</description></item>
<item><title>Bitdeer AI Johor campus (A201, A202) entered the record as announced</title><link>https://arusgrid.com/project/my-jhb-bitdeer-johor</link><guid isPermaLink="false">my-jhb-bitdeer-johor:2026-09-14:announced</guid><pubDate>Mon, 14 Sep 2026 00:00:00 +0000</pubDate><description>Bitdeer AI Johor campus (A201, A202), Johor Bahru, Malaysia. 87 MW planned IT load. Entered the record as announced on 14 September 2026.</description></item>
<item><title>Yotta NM2 entered the record as under construction</title><link>https://arusgrid.com/project/in-mum-yotta-nm2</link><guid isPermaLink="false">in-mum-yotta-nm2:2026-09-11:under_construction</guid><pubDate>Fri, 11 Sep 2026 00:00:00 +0000</pubDate><description>Yotta NM2, Panvel, India. 80 MW planned IT load. Entered the record as under construction on 11 September 2026.</description></item>
<item><title>StarMason Data Centre Campus entered the record as land and permitting</title><link>https://arusgrid.com/project/vn-hcm-starmason-shtp</link><guid isPermaLink="false">vn-hcm-starmason-shtp:2026-09-08:land_permitting</guid><pubDate>Tue, 08 Sep 2026 00:00:00 +0000</pubDate><description>StarMason Data Centre Campus, Thu Duc (SHTP), Vietnam. 60 MW planned IT load. Entered the record as land and permitting on 8 September 2026.</description></item>
<item><title>Privasia Silverstreams entered the record as land and permitting</title><link>https://arusgrid.com/project/my-prk-privasia-silverstreams</link><guid isPermaLink="false">my-prk-privasia-silverstreams:2026-09-07:land_permitting</guid><pubDate>Mon, 07 Sep 2026 00:00:00 +0000</pubDate><description>Privasia Silverstreams, Bagan Datuk, Malaysia. 35 MW planned IT load. Entered the record as land and permitting on 7 September 2026.</description></item>
<item><title>DAMAC Digital BKK01 (EDGNEX / Proen JV), Rama 9 entered the record as commissioning</title><link>https://arusgrid.com/project/th-bkk-edgnex-proen</link><guid isPermaLink="false">th-bkk-edgnex-proen:2026-09-07:commissioning</guid><pubDate>Mon, 07 Sep 2026 00:00:00 +0000</pubDate><description>DAMAC Digital BKK01 (EDGNEX / Proen JV), Rama 9, Huai Khwang (Rama 9 Road, beside Rama 9 Hospital), Thailand. 20 MW planned IT load. Entered the record as commissioning on 7 September 2026.</description></item>
<item><title>TCS HyperVault Hyderabad AI campus entered the record as land and permitting</title><link>https://arusgrid.com/project/in-hyd-hypervault-hyderabad</link><guid isPermaLink="false">in-hyd-hypervault-hyderabad:2026-09-05:land_permitting</guid><pubDate>Sat, 05 Sep 2026 00:00:00 +0000</pubDate><description>TCS HyperVault Hyderabad AI campus, Hyderabad, India. Entered the record as land and permitting on 5 September 2026.</description></item>
<item><title>Digital Edge BOM1 campus moved to operational</title><link>https://arusgrid.com/project/in-mum-digitaledge-bom1-navimumbai</link><guid isPermaLink="false">in-mum-digitaledge-bom1-navimumbai:2026-08-31:operational</guid><pubDate>Mon, 31 Aug 2026 00:00:00 +0000</pubDate><description>Digital Edge BOM1 campus, Navi Mumbai, India. 300 MW planned IT load. Moved to operational on 31 August 2026.</description></item>
<item><title>Digital Edge BOM1 campus moved to expanding</title><link>https://arusgrid.com/project/in-mum-digitaledge-bom1-navimumbai</link><guid isPermaLink="false">in-mum-digitaledge-bom1-navimumbai:2026-08-31:expanding</guid><pubDate>Mon, 31 Aug 2026 00:00:00 +0000</pubDate><description>Digital Edge BOM1 campus, Navi Mumbai, India. 300 MW planned IT load. Moved to expanding on 31 August 2026.</description></item>
<item><title>Digital Edge BOM1 campus moved to expanding</title><link>https://arusgrid.com/project/in-mum-digitaledge-bom1-navimumbai</link><guid isPermaLink="false">in-mum-digitaledge-bom1-navimumbai:2026-08-31:expanding</guid><pubDate>Mon, 31 Aug 2026 00:00:00 +0000</pubDate><description>Digital Edge BOM1 campus, Navi Mumbai, India. 300 MW planned IT load. Moved to expanding on 31 August 2026.</description></item>
<item><title>DataVolt Oxagon AI campus moved to under construction</title><link>https://arusgrid.com/project/sa-neom-datavolt-oxagon</link><guid isPermaLink="false">sa-neom-datavolt-oxagon:2026-08-31:under_construction</guid><pubDate>Mon, 31 Aug 2026 00:00:00 +0000</pubDate><description>DataVolt Oxagon AI campus, Oxagon, Saudi Arabia. 360 MW planned IT load. Moved to under construction on 31 August 2026.</description></item>
<item><title>Gulf Data Hub Abu Dhabi (ICAD) moved to expanding</title><link>https://arusgrid.com/project/ae-auh-gulfdatahub-icad</link><guid isPermaLink="false">ae-auh-gulfdatahub-icad:2026-08-28:expanding</guid><pubDate>Fri, 28 Aug 2026 00:00:00 +0000</pubDate><description>Gulf Data Hub Abu Dhabi (ICAD), Abu Dhabi, United Arab Emirates. 64 MW planned IT load. Moved to expanding on 28 August 2026.</description></item>
<item><title>CtrlS Datacenters EECd Hyperscale Campus (with National Telecom) entered the record as cancelled</title><link>https://arusgrid.com/project/th-cbi-ctrls-eecd</link><guid isPermaLink="false">th-cbi-ctrls-eecd:2026-08-28:cancelled</guid><pubDate>Fri, 28 Aug 2026 00:00:00 +0000</pubDate><description>CtrlS Datacenters EECd Hyperscale Campus (with National Telecom), Si Racha (EECd / Digital Park Thailand), Thailand. 150 MW planned IT load. Entered the record as cancelled on 28 August 2026.</description></item>
<item><title>SAIGONTEL AI Data Center, Nam Tan Tap IP entered the record as announced</title><link>https://arusgrid.com/project/vn-tni-saigontel-namtantap</link><guid isPermaLink="false">vn-tni-saigontel-namtantap:2026-08-28:announced</guid><pubDate>Fri, 28 Aug 2026 00:00:00 +0000</pubDate><description>SAIGONTEL AI Data Center, Nam Tan Tap IP, Tan Tap (Nam Tan Tap Industrial Park), Vietnam. 100 MW planned IT load. Entered the record as announced on 28 August 2026.</description></item>
<item><title>Yotta D4 entered the record as announced</title><link>https://arusgrid.com/project/in-ncr-yotta-d4</link><guid isPermaLink="false">in-ncr-yotta-d4:2026-08-27:announced</guid><pubDate>Thu, 27 Aug 2026 00:00:00 +0000</pubDate><description>Yotta D4, Greater Noida, India. 120 MW planned IT load. Entered the record as announced on 27 August 2026.</description></item>
<item><title>NEXTDC KL1 moved to expanding</title><link>https://arusgrid.com/project/my-sel-nextdc-kl1</link><guid isPermaLink="false">my-sel-nextdc-kl1:2026-08-27:expanding</guid><pubDate>Thu, 27 Aug 2026 00:00:00 +0000</pubDate><description>NEXTDC KL1, Petaling Jaya, Malaysia. 65 MW planned IT load. Moved to expanding on 27 August 2026.</description></item>
<item><title>NEXTDC Bangkok (BKK1) entered the record as announced</title><link>https://arusgrid.com/project/th-bkk-nextdc-bkk1</link><guid isPermaLink="false">th-bkk-nextdc-bkk1:2026-08-27:announced</guid><pubDate>Thu, 27 Aug 2026 00:00:00 +0000</pubDate><description>NEXTDC Bangkok (BKK1), Bangkok (north/north-east fringe), Thailand. Entered the record as announced on 27 August 2026.</description></item>
<item><title>BTC Digital AI Data Center, Nam Trang Cat IP entered the record as announced</title><link>https://arusgrid.com/project/vn-hp-btcdigital-namtrangcat</link><guid isPermaLink="false">vn-hp-btcdigital-namtrangcat:2026-08-25:announced</guid><pubDate>Tue, 25 Aug 2026 00:00:00 +0000</pubDate><description>BTC Digital AI Data Center, Nam Trang Cat IP, Hai Phong (Nam Trang Cat Industrial Park, Hai An), Vietnam. Entered the record as announced on 25 August 2026.</description></item>
<item><title>Data Centre Holdings India Anandapuram entered the record as announced</title><link>https://arusgrid.com/project/in-vtz-dchi-vizag</link><guid isPermaLink="false">in-vtz-dchi-vizag:2026-08-24:announced</guid><pubDate>Mon, 24 Aug 2026 00:00:00 +0000</pubDate><description>Data Centre Holdings India Anandapuram, Anandapuram, India. 486 MW planned IT load. Entered the record as announced on 24 August 2026.</description></item>
<item><title>ReNew AP Green Data Center entered the record as announced</title><link>https://arusgrid.com/project/in-vtz-renew-anakapalli</link><guid isPermaLink="false">in-vtz-renew-anakapalli:2026-08-24:announced</guid><pubDate>Mon, 24 Aug 2026 00:00:00 +0000</pubDate><description>ReNew AP Green Data Center, Makavaripalem, India. 1,000 MW planned IT load. Entered the record as announced on 24 August 2026.</description></item>
<item><title>AM AI Factory Vizag entered the record as announced</title><link>https://arusgrid.com/project/in-vtz-amai-vizag</link><guid isPermaLink="false">in-vtz-amai-vizag:2026-08-22:announced</guid><pubDate>Sat, 22 Aug 2026 00:00:00 +0000</pubDate><description>AM AI Factory Vizag, Bheemunipatnam, India. 512 MW planned IT load. Entered the record as announced on 22 August 2026.</description></item>
<item><title>Digital Realty Jurong Island (DC-CFA2) entered the record as announced</title><link>https://arusgrid.com/project/sg-sg-digitalrealty-jurongisland</link><guid isPermaLink="false">sg-sg-digitalrealty-jurongisland:2026-08-21:announced</guid><pubDate>Fri, 21 Aug 2026 00:00:00 +0000</pubDate><description>Digital Realty Jurong Island (DC-CFA2), Jurong Island, Singapore. 50 MW planned IT load. Entered the record as announced on 21 August 2026.</description></item>
<item><title>Equinix Jurong Island (DC-CFA2) entered the record as announced</title><link>https://arusgrid.com/project/sg-sg-equinix-jurongisland</link><guid isPermaLink="false">sg-sg-equinix-jurongisland:2026-08-21:announced</guid><pubDate>Fri, 21 Aug 2026 00:00:00 +0000</pubDate><description>Equinix Jurong Island (DC-CFA2), Jurong Island, Singapore. 50 MW planned IT load. Entered the record as announced on 21 August 2026.</description></item>
<item><title>Keppel DC SGP 11, Jurong Island (DC-CFA2) entered the record as announced</title><link>https://arusgrid.com/project/sg-sg-keppel-jurongisland</link><guid isPermaLink="false">sg-sg-keppel-jurongisland:2026-08-21:announced</guid><pubDate>Fri, 21 Aug 2026 00:00:00 +0000</pubDate><description>Keppel DC SGP 11, Jurong Island (DC-CFA2), Jurong Island, Singapore. 50 MW planned IT load. Entered the record as announced on 21 August 2026.</description></item>
<item><title>STT GDC Jurong Island (DC-CFA2) entered the record as announced</title><link>https://arusgrid.com/project/sg-sg-stt-jurongisland</link><guid isPermaLink="false">sg-sg-stt-jurongisland:2026-08-21:announced</guid><pubDate>Fri, 21 Aug 2026 00:00:00 +0000</pubDate><description>STT GDC Jurong Island (DC-CFA2), Jurong Island, Singapore. 50 MW planned IT load. Entered the record as announced on 21 August 2026.</description></item>
<item><title>DayOne Southville City Campus (ex-Mah Sing DC Hub) entered the record as land and permitting</title><link>https://arusgrid.com/project/my-sel-mahsing-southville</link><guid isPermaLink="false">my-sel-mahsing-southville:2026-08-20:land_permitting</guid><pubDate>Thu, 20 Aug 2026 00:00:00 +0000</pubDate><description>DayOne Southville City Campus (ex-Mah Sing DC Hub), Bangi, Malaysia. Entered the record as land and permitting on 20 August 2026.</description></item>
<item><title>YTL Power Sedenak Tech Park West Campus entered the record as announced</title><link>https://arusgrid.com/project/my-jhb-ytl-stepwest</link><guid isPermaLink="false">my-jhb-ytl-stepwest:2026-08-19:announced</guid><pubDate>Wed, 19 Aug 2026 00:00:00 +0000</pubDate><description>YTL Power Sedenak Tech Park West Campus, Sedenak (Kulai), Malaysia. Entered the record as announced on 19 August 2026.</description></item>
<item><title>STT VNG Ho Chi Minh City 2 entered the record as cancelled</title><link>https://arusgrid.com/project/vn-hcm-sttvng-tanthuan-2</link><guid isPermaLink="false">vn-hcm-sttvng-tanthuan-2:2026-08-18:cancelled</guid><pubDate>Tue, 18 Aug 2026 00:00:00 +0000</pubDate><description>STT VNG Ho Chi Minh City 2, District 7 (Tan Thuan EPZ), Vietnam. 60 MW planned IT load. Entered the record as cancelled on 18 August 2026.</description></item>
<item><title>AWS Thane (Balkum-Majiwada) moved to under construction</title><link>https://arusgrid.com/project/in-mum-aws-thane-balkum</link><guid isPermaLink="false">in-mum-aws-thane-balkum:2026-08-14:under_construction</guid><pubDate>Fri, 14 Aug 2026 00:00:00 +0000</pubDate><description>AWS Thane (Balkum-Majiwada), Thane, India. 272 MW planned IT load. Moved to under construction on 14 August 2026.</description></item>
<item><title>Anant Raj Cloud Manesar moved to expanding</title><link>https://arusgrid.com/project/in-ncr-anantraj-manesar</link><guid isPermaLink="false">in-ncr-anantraj-manesar:2026-08-11:expanding</guid><pubDate>Tue, 11 Aug 2026 00:00:00 +0000</pubDate><description>Anant Raj Cloud Manesar, Manesar, India. 50 MW planned IT load. Moved to expanding on 11 August 2026.</description></item>
<item><title>Anant Raj Cloud Rai entered the record as under construction</title><link>https://arusgrid.com/project/in-ncr-anantraj-rai</link><guid isPermaLink="false">in-ncr-anantraj-rai:2026-08-11:under_construction</guid><pubDate>Tue, 11 Aug 2026 00:00:00 +0000</pubDate><description>Anant Raj Cloud Rai, Rai, Sonipat, India. 200 MW planned IT load. Entered the record as under construction on 11 August 2026.</description></item>
<item><title>Narra Technology Park hyperscale campus entered the record as cancelled</title><link>https://arusgrid.com/project/ph-tar-endec-narra-technology-park</link><guid isPermaLink="false">ph-tar-endec-narra-technology-park:2026-08-11:cancelled</guid><pubDate>Tue, 11 Aug 2026 00:00:00 +0000</pubDate><description>Narra Technology Park hyperscale campus, Capas / Bamban (New Clark City), Philippines. 300 MW planned IT load. Entered the record as cancelled on 11 August 2026.</description></item>
<item><title>Zankore AI Factory, Batang entered the record as announced</title><link>https://arusgrid.com/project/id-batang-zankore-aifactory</link><guid isPermaLink="false">id-batang-zankore-aifactory:2026-08-07:announced</guid><pubDate>Fri, 07 Aug 2026 00:00:00 +0000</pubDate><description>Zankore AI Factory, Batang, Batang, Indonesia. 200 MW planned IT load. Entered the record as announced on 7 August 2026.</description></item>
<item><title>Digital Cosmos Cyberjaya entered the record as land and permitting</title><link>https://arusgrid.com/project/my-sel-digitalcosmos-cyberjaya</link><guid isPermaLink="false">my-sel-digitalcosmos-cyberjaya:2026-08-07:land_permitting</guid><pubDate>Fri, 07 Aug 2026 00:00:00 +0000</pubDate><description>Digital Cosmos Cyberjaya, Cyberjaya, Malaysia. Entered the record as land and permitting on 7 August 2026.</description></item>
<item><title>DPS Resources Bukit Rambai Data Centre entered the record as announced</title><link>https://arusgrid.com/project/my-mlk-dps-bukitrambai</link><guid isPermaLink="false">my-mlk-dps-bukitrambai:2026-08-07:announced</guid><pubDate>Fri, 07 Aug 2026 00:00:00 +0000</pubDate><description>DPS Resources Bukit Rambai Data Centre, Melaka, Malaysia. 89 MW planned IT load. Entered the record as announced on 7 August 2026.</description></item>
<item><title>Microsoft Hyderabad Chandanvelly campus (HYD11) moved to operational</title><link>https://arusgrid.com/project/in-hyd-microsoft-chandanvelly</link><guid isPermaLink="false">in-hyd-microsoft-chandanvelly:2026-08-06:operational</guid><pubDate>Thu, 06 Aug 2026 00:00:00 +0000</pubDate><description>Microsoft Hyderabad Chandanvelly campus (HYD11), Chandanvelly, India. Moved to operational on 6 August 2026.</description></item>